GlaxoSmithKline Wind Project (Turbine 4)

GlaxoSmithKline Wind Project (Turbine 4) is operational in North Ayrshire with a recorded capacity of 2.5 MW, and has been generating since 2014-06-01.

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-06-01
Wind Onshore
Technology
GlaxoSmithKline
North Ayrshire
Authority
Scotland

Planning and build timeline

Application submitted2012-11-13
Permission granted2013-06-19
7 months after submission
Operational2014-06-01
11 months after consent

North Ayrshire’s record on onshore wind

North Ayrshire has decided 18 onshore wind schemes and approved 78%, taking a median of 8.5 months. See every onshore wind scheme decision in North Ayrshire

Other built sites within 15 km

SiteMWDistance
Glaxosmithkline Shewalton Road
Solar Photovoltaics · Under Construction
19.90.7 km
GlaxoSmithKline (Waste AD)
Anaerobic Digestion · Operational
10.8 km
Shewalton Road
Wind Onshore · Under Construction
31 km
GlaxoSmithKline Wind Project
Wind Onshore · Operational
7.51.1 km
Oldhall Industrial Estate
EfW Incineration · Under Construction
171.4 km
Caledonian Papermill
Biomass (dedicated) · Operational
262 km
Shewalton Landfill Solar Farm
Solar Photovoltaics · Under Construction
52.1 km
Nethermains - Solar Farm
Solar Photovoltaics · Under Construction
7.54.2 km

How big is GlaxoSmithKline Wind Project (Turbine 4)?

GlaxoSmithKline Wind Project (Turbine 4) has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates GlaxoSmithKline Wind Project (Turbine 4)?

REPD records the operator as GlaxoSmithKline. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was GlaxoSmithKline Wind Project (Turbine 4) approved and built?

The application was submitted on 2012-11-13. Permission was granted on 2013-06-19, 7 months later. The site became operational on 2014-06-01, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4370.