GlaxoSmithKline Wind Project (Turbine 4)
GlaxoSmithKline Wind Project (Turbine 4) is operational in North Ayrshire with a recorded capacity of 2.5 MW, and has been generating since 2014-06-01.
Planning and build timeline
| Application submitted | 2012-11-13 |
| Permission granted | 2013-06-19 7 months after submission |
| Operational | 2014-06-01 11 months after consent |
North Ayrshire’s record on onshore wind
North Ayrshire has decided 18 onshore wind schemes and approved 78%, taking a median of 8.5 months. See every onshore wind scheme decision in North Ayrshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Glaxosmithkline Shewalton Road Solar Photovoltaics · Under Construction | 19.9 | 0.7 km |
GlaxoSmithKline (Waste AD) Anaerobic Digestion · Operational | 1 | 0.8 km |
Shewalton Road Wind Onshore · Under Construction | 3 | 1 km |
GlaxoSmithKline Wind Project Wind Onshore · Operational | 7.5 | 1.1 km |
Oldhall Industrial Estate EfW Incineration · Under Construction | 17 | 1.4 km |
Caledonian Papermill Biomass (dedicated) · Operational | 26 | 2 km |
Shewalton Landfill Solar Farm Solar Photovoltaics · Under Construction | 5 | 2.1 km |
Nethermains - Solar Farm Solar Photovoltaics · Under Construction | 7.5 | 4.2 km |
How big is GlaxoSmithKline Wind Project (Turbine 4)?
GlaxoSmithKline Wind Project (Turbine 4) has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates GlaxoSmithKline Wind Project (Turbine 4)?
REPD records the operator as GlaxoSmithKline. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was GlaxoSmithKline Wind Project (Turbine 4) approved and built?
The application was submitted on 2012-11-13. Permission was granted on 2013-06-19, 7 months later. The site became operational on 2014-06-01, 11 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4370.