Renewable sites › Sneddon Law Community Wind Farm
Sneddon Law Community Wind Farm
Sneddon Law Community Wind Farm is a 45 MW onshore wind farm under construction in East Ayrshire. Planning permission was granted on 28 February 2013, 14 months after submission. Operator of record: Community Windpower.
Planning and build timeline
| Application submitted | 11 January 2012 |
| Permission granted | 28 February 2013 14 months after submission |
| Operational | not recorded |
Screening a site of your own?
East Ayrshire approves 45% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Sneddon Law Community Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
East Ayrshire’s record on onshore wind
East Ayrshire has decided 20 onshore wind schemes and approved 45%, taking a median of 29.7 months. See every onshore wind scheme decision in East Ayrshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 109 | 4.9 km |
Solar Photovoltaics · Operational | — | 7.2 km |
Wind Onshore · Operational | 108 | 7.8 km |
Wind Onshore · Operational | 322 | 8.4 km |
Battery · Operational | 300 | 8.6 km |
Wind Onshore · Operational | 4.7 | 8.7 km |
Wind Onshore · Operational | 1.8 | 9.1 km |
Landfill Gas · Operational | 2.4 | 11.1 km |
How big is Sneddon Law Community Wind Farm?
Sneddon Law Community Wind Farm has a recorded installed capacity of 45 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Sneddon Law Community Wind Farm?
REPD records the operator as Community Windpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Sneddon Law Community Wind Farm approved and built?
The application was submitted on 11 January 2012. Permission was granted on 28 February 2013, 14 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4128.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode