J3 Business Park - Battery Energy Storage Facility

J3 Business Park - Battery Energy Storage Facility is under construction in Doncaster with a recorded capacity of 10 MW.

10 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Forepower Limited
Doncaster
Authority
England

Planning and build timeline

Application submitted2022-10-26
Permission granted2023-01-24
3 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Doncaster’s record on battery storage

Doncaster has decided 10 battery storage schemes and approved 100%, taking a median of 5.1 months. See every battery storage scheme decision in Doncaster

Other built sites within 15 km

SiteMWDistance
Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD)
Anaerobic Digestion · Operational
23.8 km
Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD) - extension
Anaerobic Digestion · Operational
33.8 km
Next Distribution Centre Doncaster
Solar Photovoltaics · Operational
2.57.4 km
Ikea Distribution Centre
Solar Photovoltaics · Operational
1.77.6 km
Marr Windfarm
Wind Onshore · Operational
88.1 km
Trackwork Limited (EfW)
EfW Incineration · Operational
39.2 km
Croft Farm, Askern Road - Solar Array & Hydrogen Plant
Solar Photovoltaics · Under Construction
2.59.3 km
Misson Solar Farm
Solar Photovoltaics · Operational
511.7 km

How big is J3 Business Park - Battery Energy Storage Facility?

J3 Business Park - Battery Energy Storage Facility has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates J3 Business Park - Battery Energy Storage Facility?

REPD records the operator as Forepower Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was J3 Business Park - Battery Energy Storage Facility approved and built?

The application was submitted on 2022-10-26. Permission was granted on 2023-01-24, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12920.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council