Marr Windfarm

Marr Windfarm is operational in Doncaster with a recorded capacity of 8 MW, and has been generating since 2012-01-18.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-01-18
Wind Onshore
Technology
Banks Renewables
Doncaster
Authority
England

Planning and build timeline

Application submitted2006-12-20
Permission granted2007-07-17
7 months after submission
Operational2012-01-18
54 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Doncaster’s record on onshore wind

Doncaster has decided 5 onshore wind schemes and approved 80%, taking a median of 49.2 months. See every onshore wind scheme decision in Doncaster

Other built sites within 15 km

SiteMWDistance
Hampole Wind Farm
Wind Onshore · Operational
85 km
Goldthorpe
Solar Photovoltaics · Operational
1.55.1 km
Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD)
Anaerobic Digestion · Operational
45.8 km
Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD) - extension
Anaerobic Digestion · Operational
36.8 km
Prosper Demulder Limited Anaerobic Digestion Plant (Waste AD)
Anaerobic Digestion · Operational
26.8 km
Croft Farm, Askern Road - Solar Array & Hydrogen Plant
Solar Photovoltaics · Under Construction
2.56.8 km
Skelbrooke Landfill Gas Project
Landfill Gas · Operational
2.17.4 km
Elmsall Way Warehouse
Solar Photovoltaics · Operational
2.47.9 km

How big is Marr Windfarm?

Marr Windfarm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Marr Windfarm?

REPD records the operator as Banks Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Marr Windfarm approved and built?

The application was submitted on 2006-12-20. Permission was granted on 2007-07-17, 7 months later. The site became operational on 2012-01-18, 54 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3963.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council