Novarly ParcelRenewable sites

Renewable sitesMisson Solar Farm

Misson Solar Farm

Misson Solar Farm is an operational 5 MW solar farm in Bassetlaw, generating since 24 March 2016. Planning permission was granted on 27 October 2015, 8 months after submission. Operator of record: Novus.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 24 March 2016
Solar Photovoltaics
Technology
Novus
Bassetlaw
Authority
England

Planning and build timeline

Application submitted18 February 2015
Permission granted27 October 2015
8 months after submission
Operational24 March 2016
5 months after consent

Screening a site of your own?

RedlineUK · £39

Bassetlaw approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Misson Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bassetlaw’s record on solar

Bassetlaw has decided 23 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in Bassetlaw

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
39.3 km
Solar Photovoltaics · Operational
59.5 km
Solar Photovoltaics · Operational
410 km
Solar Photovoltaics · Operational
2.510.9 km
Solar Photovoltaics · Operational
1.711.1 km
Solar Photovoltaics · Operational
1.711.4 km
Solar Photovoltaics · Under Construction
49.911.4 km
Solar Photovoltaics · Operational
811.5 km

How big is Misson Solar Farm?

Misson Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Misson Solar Farm?

REPD records the operator as Novus. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Misson Solar Farm approved and built?

The application was submitted on 18 February 2015. Permission was granted on 27 October 2015, 8 months later. The site became operational on 24 March 2016, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6181.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode