Novarly ParcelRenewable sites

Renewable sitesHSH Coldstores, Estate Road - Solar Panels

HSH Coldstores, Estate Road - Solar Panels

HSH Coldstores, Estate Road - Solar Panels is an operational 1.08 MW solar farm in North East Lincolnshire, generating since 10 January 2024. Planning permission was granted on 10 May 2023, 2 months after submission. Operator of record: HSH Coldstores.

1.08 MW
Capacity
as recorded in REPD
Operational
Status
since 10 January 2024
Solar Photovoltaics
Technology
HSH Coldstores
North East Lincolnshire
Authority
England

Planning and build timeline

Application submitted1 March 2023
Permission granted10 May 2023
2 months after submission
Operational10 January 2024
8 months after consent

Screening a site of your own?

RedlineUK · £39

North East Lincolnshire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with HSH Coldstores, Estate Road - Solar Panels’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North East Lincolnshire’s record on solar

North East Lincolnshire has decided 27 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North East Lincolnshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.121.4 km
Solar Photovoltaics · Under Construction
0.363.4 km
Solar Photovoltaics · Under Construction
49.93.8 km
EfW Incineration · Operational
3.24.1 km
Solar Photovoltaics · Operational
204.7 km
Battery · Under Construction
805.2 km
Solar Photovoltaics · Operational
27.15.8 km
Landfill Gas · Operational
16 km

How big is HSH Coldstores, Estate Road - Solar Panels?

HSH Coldstores, Estate Road - Solar Panels has a recorded installed capacity of 1.08 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates HSH Coldstores, Estate Road - Solar Panels?

REPD records the operator as HSH Coldstores. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was HSH Coldstores, Estate Road - Solar Panels approved and built?

The application was submitted on 1 March 2023. Permission was granted on 10 May 2023, 2 months later. The site became operational on 10 January 2024, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 13381.

Novarly Parcel · official public data, read properly · parcel.novarly.com