Grimsby Solar Farm

Grimsby Solar Farm is a 49.9 MW solar farm under construction in North East Lincolnshire. Planning permission was granted on 25 November 2022, 14 months after submission. Operator of record: Aura Power.

49.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Aura Power
North East Lincolnshire
Authority
England

Planning and build timeline

Application submitted7 October 2021
Permission granted25 November 2022
14 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

North East Lincolnshire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Grimsby Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North East Lincolnshire’s record on solar

North East Lincolnshire has decided 27 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North East Lincolnshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.083.8 km
Solar Photovoltaics · Operational
204 km
Solar Photovoltaics · Operational
27.14.3 km
EfW Incineration · Operational
3.24.7 km
Solar Photovoltaics · Operational
1.125.1 km
Battery · Under Construction
805.2 km
Landfill Gas · Operational
16 km
Landfill Gas · Operational
26 km

How big is Grimsby Solar Farm?

Grimsby Solar Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Grimsby Solar Farm?

REPD records the operator as Aura Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Grimsby Solar Farm approved and built?

The application was submitted on 7 October 2021. Permission was granted on 25 November 2022, 14 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7889.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode