Renewable planning › Solar › North East Lincolnshire
Solar planning in North East Lincolnshire
North East Lincolnshire has decided 27 solar farms and approved 96% of them, taking a median of 2.7 months to decide. Consented capacity: 221 MW. 2 applications still awaiting a decision.
How North East Lincolnshire compares
Against the 298 UK authorities with 5+ solar decisions, North East Lincolnshire sits in the 47th percentile for approval rate (3 points above the England average) and the 42nd percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (32)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Diana Princess Of Wales Hospital - Solar Panels Northern Lincolnshire and Goole NHS Foundation Trust · DM/1045/25/PNSOLC · 1.7 mo to decide | 0.81 | Awaiting Construction | 2026-02-02 |
Daniels Chilled Foods, Lakeside - Solar Panels Daniels Group · DM/0490/25/PNSOL · 1.6 mo to decide | 0.81 | Awaiting Construction | 2025-07-30 |
Gorton Street & Murray Street, Grimsby Docks - Solar PV Panels GY 1900 Limited · DM/0188/25/FUL · 4 mo to decide | 1.5 | Awaiting Construction | 2025-07-14 |
Murray Street, Grimsby Docks - Solar PV Panels GY 1900 Limited · DM/0187/25/FUL · 4 mo to decide | 0.8 | Awaiting Construction | 2025-07-14 |
Stallingboroughe, Stallingborough Road - Solar PV Energy Island Green Power · DM/0455/25/FUL | 37.4 | Application Submitted | 2025-06-30 |
Armadillo Self Storage, The Deans, 1 Estate Road - Solar Photovoltaic Big Yellow Self Storage Limited · DM/0361/25/PNSOL · 1.6 mo to decide | 0.15 | Awaiting Construction | 2025-06-24 |
Immingham Solar Farm - Solar Farm One Planet Developments Limited · DM/0108/24/FUL · 14.4 mo to decide | 49.9 | Awaiting Construction | 2025-05-06 |
MRS Coldstore, Norfolk Lane - Solar PV Panels M.R.S. Cold Stores Limited · DM/0194/24/PNSOL · 7.5 mo to decide | 0.45 | Application Refused | 2024-10-08 |
Manor Golf Course, Barton Street - Solar Panels Laceby Manor Resort Limited · DM/0150/24/FUL · 5.9 mo to decide | — | Awaiting Construction | 2024-09-25 |
Freshney Green Primary Care Centre, Sorrel Road - Solar panels Assura Aspire Limited · DM/1227/23/PNSOL · 1.8 mo to decide | 0.19 | Awaiting Construction | 2024-05-15 |
Bradley Road - Solar Farm Renewable Connections Developments Limited · DM/1156/23/FUL · 4.9 mo to decide | 43.7 | Awaiting Construction | 2024-04-26 |
Abp Border Control Post Building, Queens Road - Solar Photovoltaic Panel Associated British Ports · DM/0823/23/PNSOL · 1.7 mo to decide | 0.43 | Awaiting Construction | 2023-10-09 |
Shed 10, Alexandra Road South, Immingham Docks - Solar Panels Associated British Ports (Head Office) · DM/0697/23/FUL · 1.7 mo to decide | 1.37 | Awaiting Construction | 2023-09-11 |
Shed 27, Alexandra Road, South Immingham - Solar Photovoltaic Panels Associated British Ports (Head Office) · DM/0698/23/FUL · 1.7 mo to decide | 1.07 | Awaiting Construction | 2023-09-11 |
Grimsby West, Birchin Way - Solar Array HSH Coldstores · DM/0127/23/FUL · 2.5 mo to decide | 1.12 | Operational | 2023-05-17 |
HSH Coldstores, Estate Road - Solar Panels HSH Coldstores · DM/0083/23/FUL · 2.3 mo to decide | 1.08 | Operational | 2023-05-10 |
Thorpe Park Holiday Camp, Anthonys Bank Road - Solar Panels Bourne Leisure Limited · DM/0188/23/PNSOL · 2.7 mo to decide | 0.57 | Awaiting Construction | 2023-04-27 |
Weelsby Pumping Station, Hewitts Avenue - Solar Panels Anglian Water Services Litimited · DM/0946/22/CEA · 5.3 mo to decide | 0.38 | Awaiting Construction | 2023-04-26 |
Grimsby Solar Farm Aura Power · DM/0899/21/FUL · 13.6 mo to decide | 49.9 | Under Construction | 2022-11-25 |
Grimsby Institute, Laceby Road - Solar Panels Grimsby Institute Of Higher And Further Education · DM/0823/22/PNSOL · 1.8 mo to decide | 0.19 | Awaiting Construction | 2022-11-07 |
Macaulay Lane Solar Farm SEC Power 3 Limited · DM/0331/21/FUL | 8 | Application Withdrawn | 2022-09-09 |
N H Case Limited - Solar Panels N H Case Limited · DM/0957/21/PNSOL · 10.9 mo to decide | 0.36 | Under Construction | 2022-08-17 |
Estate Road - Solar Panels DFDS · DM/0284/22/PNSOL · 1.6 mo to decide | 0.66 | Awaiting Construction | 2022-05-19 |
Hilmore Road, Laceby - Photovoltaic Solar System WM Morrisons Supermarkets Plc · DM/0099/22/PNSOL · 2.7 mo to decide | 0.45 | Awaiting Construction | 2022-05-10 |
Innovation Centre - Solar PV North East Lincolnshire Council · DM/1206/21/PNSOL | — | Application Submitted | 2021-12-10 |
Mauxhall Farm ENGIE Renewables · DM/1145/19/FUL · 5.4 mo to decide | 18 | Planning Permission Expired | 2020-05-28 |
Oasis Academy Wintringham Oasis Community Learning / Eden Sustainable · DM/0895/19/PNSOL · 1.5 mo to decide | 0.2 | Awaiting Construction | 2020-03-23 |
Hewitts Avenue Tesco Push Energy · DM/1109/18/PNSOL · 2.5 mo to decide | 0.5 | Operational | 2019-03-13 |
Low Farm Solar Array Wirsol / Island Green Power · DM/0483/15/FUL · 3.5 mo to decide | 20 | Operational | 2015-10-09 |
Laceby Solar Farm Conergy · DM/0174/15/FUL · 3.5 mo to decide | 27.1 | Operational | 2015-06-19 |
West Marsh (Phase 2) Millennium Park (Grimsby) Ltd · DM/1124/14/FUL · 3.4 mo to decide | 5 | Abandoned | 2015-02-13 |
West Marsh (Phase 1) Millennium Park (Grimsby) Ltd · DM/1120/14/FUL · 3.4 mo to decide | 2 | Abandoned | 2015-02-13 |
Does North East Lincolnshire approve solar farms?
Yes — of the 27 solar farms North East Lincolnshire has decided, 96% were approved (26 granted, 1 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in North East Lincolnshire?
The median time from application to decision is 2.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has North East Lincolnshire consented?
221 MW has been consented across 26 approved schemes. A further 2 applications awaits a decision.
Other technologies in North East Lincolnshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.