Laceby Solar Farm

Laceby Solar Farm is an operational 27.1 MW solar farm in North East Lincolnshire, generating since 22 June 2016. Planning permission was granted on 19 June 2015, 3 months after submission. Operator of record: Conergy.

27.1 MW
Capacity
as recorded in REPD
Operational
Status
since 22 June 2016
Solar Photovoltaics
Technology
Conergy
North East Lincolnshire
Authority
England

Planning and build timeline

Application submitted5 March 2015
Permission granted19 June 2015
3 months after submission
Operational22 June 2016
12 months after consent

Screening a site of your own?

RedlineUK · £39

North East Lincolnshire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Laceby Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North East Lincolnshire’s record on solar

North East Lincolnshire has decided 27 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North East Lincolnshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
201.2 km
Solar Photovoltaics · Under Construction
49.94.3 km
Solar Photovoltaics · Operational
1.085.8 km
Solar Photovoltaics · Operational
1.126.3 km
Solar Photovoltaics · Operational
0.56.8 km
Solar Photovoltaics · Under Construction
0.367.6 km
EfW Incineration · Operational
3.28.6 km
Battery · Under Construction
809.3 km

How big is Laceby Solar Farm?

Laceby Solar Farm has a recorded installed capacity of 27.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Laceby Solar Farm?

REPD records the operator as Conergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Laceby Solar Farm approved and built?

The application was submitted on 5 March 2015. Permission was granted on 19 June 2015, 3 months later. The site became operational on 22 June 2016, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4880.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode