Great Wheatley Road - Solar Farm is under construction in Rochford with a recorded capacity of 30 MW.
Planning and build timeline
| Application submitted | 2022-03-17 |
| Permission granted | 2024-03-11 24 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Rochford’s record on solar
Rochford has decided 7 solar farms and approved 100%, taking a median of 5.7 months. See every solar farm decision in Rochford →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dollymans Storage Battery · Operational | 99.98 | 2.7 km |
London Southend Airport Solar Photovoltaics · Operational | 2.5 | 6.7 km |
Tesco Extra Hazelmere Solar Photovoltaics · Operational | 0.4 | 6.9 km |
Nevendon Battery Storage Extension Battery · Operational | 5 | 7.2 km |
Nevendon Battery · Operational | 10 | 7.2 km |
Pitsea Landfill Scheme Landfill Gas · Operational | 11.6 | 7.8 km |
Pitsea Tipp Landfill Gas · Operational | 14 | 7.9 km |
South Fambridge Hall - Solar farm & Battery storage Solar Photovoltaics · Under Construction | 49.99 | 8.1 km |
How big is Great Wheatley Road - Solar Farm?
Great Wheatley Road - Solar Farm has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Great Wheatley Road - Solar Farm?
REPD records the operator as Aura Power Solar UK Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Great Wheatley Road - Solar Farm approved and built?
The application was submitted on 2022-03-17. Permission was granted on 2024-03-11, 24 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9802.