London Southend Airport is operational in Rochford with a recorded capacity of 2.5 MW, and has been generating since 2016-01-12.
Planning and build timeline
| Application submitted | 2015-03-27 |
| Permission granted | 2015-05-29 2 months after submission |
| Operational | 2016-01-12 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Rochford’s record on solar
Rochford has decided 7 solar farms and approved 100%, taking a median of 5.7 months. See every solar farm decision in Rochford →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Fambridge Road/Canewdon Road Solar Photovoltaics · Operational | 5 | 5 km |
South Fambridge Hall - Solar farm & Battery storage Solar Photovoltaics · Under Construction | 49.99 | 5.8 km |
South Fambridge Hall - Solar farm & Battery storage Battery · Under Construction | 20 | 5.8 km |
Great Wheatley Road - Solar Farm Solar Photovoltaics · Under Construction | 30 | 6.7 km |
Barling Hall Farm Landfill Gas · Operational | 2.4 | 6.9 km |
Dollymans Storage Battery · Operational | 99.98 | 9.2 km |
Wick Farm (Burnham on Crouch) Solar Photovoltaics · Operational | 5 | 11.8 km |
Tesco Extra Hazelmere Solar Photovoltaics · Operational | 0.4 | 13.4 km |
How big is London Southend Airport?
London Southend Airport has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates London Southend Airport?
REPD records the operator as London Southend Airport Co.. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was London Southend Airport approved and built?
The application was submitted on 2015-03-27. Permission was granted on 2015-05-29, 2 months later. The site became operational on 2016-01-12, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5946.