Dragon Energy Park - Wind Farm is a 14.4 MW onshore wind farm under construction in Wales. Planning permission was granted on 30 October 2024, 16 months after submission. Operator of record: Dragon LNG.

14.4 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Dragon LNG
National
Authority
Wales

Planning and build timeline

Application submitted10 July 2023
Permission granted30 October 2024
16 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dragon Energy Park - Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Welsh Government (NSIP)’s record on onshore wind

Welsh Government (NSIP) has decided 12 onshore wind schemes and approved 67%, taking a median of 15.1 months. See every onshore wind scheme decision in Welsh Government (NSIP)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
8.21.2 km
Solar Photovoltaics · Operational
9.91.4 km
Wind Onshore · Operational
3.21.9 km
Solar Photovoltaics · Operational
53.9 km
Solar Photovoltaics · Operational
105 km
Wind Onshore · Operational
15.3 km
Solar Photovoltaics · Operational
5.35.3 km
Solar Photovoltaics · Operational
245.5 km

How big is Dragon Energy Park - Wind Farm?

Dragon Energy Park - Wind Farm has a recorded installed capacity of 14.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dragon Energy Park - Wind Farm?

REPD records the operator as Dragon LNG. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dragon Energy Park - Wind Farm approved and built?

The application was submitted on 10 July 2023. Permission was granted on 30 October 2024, 16 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10304.