Wogaston Solar Farm

Wogaston Solar Farm is an operational 5.3 MW solar farm in Pembrokeshire, generating since 17 March 2015. Planning permission was granted on 16 April 2014, 16 months after submission. Operator of record: Elgin Energy EsCo.

5.3 MW
Capacity
as recorded in REPD
Operational
Status
since 17 March 2015
Solar Photovoltaics
Technology
Elgin Energy EsCo
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted21 December 2012
Permission granted16 April 2014
16 months after submission
Operational17 March 2015
11 months after consent

Screening a site of your own?

RedlineUK · £39

Pembrokeshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Wogaston Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Pembrokeshire’s record on solar

Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
100.6 km
Solar Photovoltaics · Operational
9.94.1 km
Wind Onshore · Operational
8.24.1 km
Wind Onshore · Under Construction
14.45.3 km
Wind Onshore · Operational
3.25.8 km
Solar Photovoltaics · Operational
55.8 km
Solar Photovoltaics · Operational
85.8 km
Wind Onshore · Operational
17 km

How big is Wogaston Solar Farm?

Wogaston Solar Farm has a recorded installed capacity of 5.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wogaston Solar Farm?

REPD records the operator as Elgin Energy EsCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wogaston Solar Farm approved and built?

The application was submitted on 21 December 2012. Permission was granted on 16 April 2014, 16 months later. The site became operational on 17 March 2015, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5232.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode