Renewable sites › Castle Pill - Repowering
Castle Pill - Repowering
Castle Pill - Repowering is operational in Pembrokeshire with a recorded capacity of 3.2 MW, and has been generating since 2009-06-01.
Planning and build timeline
| Application submitted | 2005-06-22 |
| Permission granted | 2005-12-19 6 months after submission |
| Operational | 2009-06-01 41 months after consent |
Pembrokeshire’s record on onshore wind
Pembrokeshire has decided 15 onshore wind schemes and approved 47%, taking a median of 8 months. See every onshore wind scheme decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dragon Energy Park - Wind Farm Wind Onshore · Under Construction | 14.4 | 1.9 km |
Dragon Long Meadow - Solar farm Solar Photovoltaics · Operational | 9.9 | 2 km |
Liddeston Ridge Solar Park (Milford Haven) Solar Photovoltaics · Operational | 5 | 2.2 km |
Wear Point Wind Onshore · Operational | 8.2 | 2.3 km |
Lodge Farm 1 Wind Onshore · Operational | 1 | 3.4 km |
Tiers Cross Solar Farm Solar Photovoltaics · Operational | 24 | 3.8 km |
Bolton Hill WTW Solar Photovoltaics · Operational | 0.5 | 4.5 km |
Hoplass Farm Solar Photovoltaics · Operational | 10 | 5.6 km |
How big is Castle Pill - Repowering?
Castle Pill - Repowering has a recorded installed capacity of 3.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Castle Pill - Repowering?
REPD records the operator as John Laing Environmental Assets Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Castle Pill - Repowering approved and built?
The application was submitted on 2005-06-22. Permission was granted on 2005-12-19, 6 months later. The site became operational on 2009-06-01, 41 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3313.
Novarly Parcel · official public data, read properly · parcel.novarly.com