Novarly ParcelRenewable sites

Renewable sitesLiddeston Ridge Solar Park (Milford Haven)

Liddeston Ridge Solar Park (Milford Haven)

Liddeston Ridge Solar Park (Milford Haven) is an operational 5 MW solar farm in Pembrokeshire, generating since 31 March 2014. Planning permission was granted on 24 January 2013, 4 months after submission. Operator of record: Milford Haven Port Authority.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2014
Solar Photovoltaics
Technology
Milford Haven Port Authority
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted2 October 2012
Permission granted24 January 2013
4 months after submission
Operational31 March 2014
14 months after consent

Screening a site of your own?

RedlineUK · £39

Pembrokeshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Liddeston Ridge Solar Park (Milford Haven)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Pembrokeshire’s record on solar

Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
11.5 km
Wind Onshore · Operational
3.22.2 km
Solar Photovoltaics · Operational
9.93.3 km
Solar Photovoltaics · Operational
243.4 km
Wind Onshore · Operational
8.23.7 km
Wind Onshore · Under Construction
14.43.9 km
Solar Photovoltaics · Operational
0.55 km
Solar Photovoltaics · Operational
5.35.8 km

How big is Liddeston Ridge Solar Park (Milford Haven)?

Liddeston Ridge Solar Park (Milford Haven) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Liddeston Ridge Solar Park (Milford Haven)?

REPD records the operator as Milford Haven Port Authority. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Liddeston Ridge Solar Park (Milford Haven) approved and built?

The application was submitted on 2 October 2012. Permission was granted on 24 January 2013, 4 months later. The site became operational on 31 March 2014, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1634.