Renewable sites › Tiers Cross Solar Farm
Tiers Cross Solar Farm
Tiers Cross Solar Farm is operational in Pembrokeshire with a recorded capacity of 24 MW, and has been generating since 2014-10-25.
Planning and build timeline
| Application submitted | 2013-05-24 |
| Permission granted | 2013-10-14 5 months after submission |
| Operational | 2014-10-25 12 months after consent |
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bolton Hill WTW Solar Photovoltaics · Operational | 0.5 | 2 km |
Lodge Farm 1 Wind Onshore · Operational | 1 | 2.9 km |
Liddeston Ridge Solar Park (Milford Haven) Solar Photovoltaics · Operational | 5 | 3.4 km |
Castle Pill - Repowering Wind Onshore · Operational | 3.2 | 3.8 km |
Lawrence Landfill Wind Onshore · Operational | 1.6 | 3.9 km |
Popehill Farm Solar Photovoltaics · Operational | 5 | 4.6 km |
North Tenement Solar Photovoltaics · Operational | 5 | 4.8 km |
Dragon Energy Park - Wind Farm Wind Onshore · Under Construction | 14.4 | 5.5 km |
How big is Tiers Cross Solar Farm?
Tiers Cross Solar Farm has a recorded installed capacity of 24 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tiers Cross Solar Farm?
REPD records the operator as Good Energy Generation. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tiers Cross Solar Farm approved and built?
The application was submitted on 2013-05-24. Permission was granted on 2013-10-14, 5 months later. The site became operational on 2014-10-25, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2074.