Renewable planning › Onshore wind › Welsh Government (NSIP)
Onshore wind planning in Welsh Government (NSIP)
Welsh Government (NSIP) has decided 12 onshore wind schemes and approved 67% of them, taking a median of 15.1 months to decide. Consented capacity: 369 MW. 8 applications still awaiting a decision.
How Welsh Government (NSIP) compares
Against the 75 UK authorities with 5+ onshore wind decisions, Welsh Government (NSIP) sits in the 45th percentile for approval rate (1 points below the England average) and the 43rd percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (20)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Y Bryn Wind Farm ESB / Coriolis Energy · DNS/3264571 · 23.1 mo to decide | 130 | Application Refused | 2025-11-21 |
Convatec Green Manufacturing Hub Convatec Limited · CAS-02977-Y9F1W7 · 7.6 mo to decide | 15 | Application Refused | 2025-11-19 |
Radnor Forest, Llandegley - Nant Mithil Energy Park Bute Energy · DNS - CAS-01907-D7Q6Z1 | 198 | Application Submitted | 2025-10-21 |
Alwen Forest Project RWE Generation / Innogy · DNS/3214855 · 12.4 mo to decide | 59.4 | Awaiting Construction | 2025-10-02 |
Gaerwen Wind Farm RWE Renewables UK Limited · DNS/3276735 | 59.4 | Application Submitted | 2025-07-30 |
Mynydd Llanhilleth - Wind Farm Pennant Walters · CAS-03540-M8J8M5 | 34 | Application Submitted | 2025-05-23 |
Pen March Wind Farm RWE Renewables UK Limited · DNS/3253147 · 16.4 mo to decide | 30 | Application Refused | 2025-03-03 |
Mynydd Maen - Wind Farm RES Limited · DNS/3276725 | 54.6 | Application Submitted | 2025-02-25 |
Tonmawr - Mynydd Fforch Dwm Wind Farm Naturalis Energy Developments Limited · DNS/3255801 · 13.7 mo to decide | 35 | Awaiting Construction | 2024-12-23 |
Twyn Hywel Wind Farm Bute Energy · DNS/3272053 · 17 mo to decide | 92.4 | Awaiting Construction | 2024-11-05 |
Dragon Energy Park - Wind Farm Dragon LNG · CAS-01859-K1M7Y6 · 15.7 mo to decide | 14.4 | Under Construction | 2024-10-30 |
Garn Fach Wind Farm EDF Renewables · DNS/3244499 · 29 mo to decide | 85 | Awaiting Construction | 2024-10-22 |
Manmoel Wind Farm Cenin Renewables · DNS/3239181 · 14.4 mo to decide | 28 | Awaiting Construction | 2024-10-16 |
Abertillery - Wind farm RWE Renewables UK Limited · DNS/3278009 | 39.6 | Application Submitted | 2024-10-11 |
Mynydd Llanhilleth - Wind Farm Pennant Walters · DNS/3273368 | 34 | Revised | 2024-06-21 |
Mynydd Y Glyn Wind Farm, Rhondda - Wind Turbines Pennant Wind Energy Ventures Limited Walters Group · DNS/3280378 · 12.7 mo to decide | 30 | Awaiting Construction | 2024-06-14 |
Trecelyn Wind Farm Pennant Walters Limited · DNS CAS-02114-J9X4S6 | 20 | Application Submitted | 2024-06-13 |
Mynydd Carn Wind Farm Pennant Walters · DNS/3270299 | 34 | Application Submitted | 2022-11-23 |
Rhoscrowther - Turbine Wind Farm Rhoscrowther Wind Farm Limited · DNS/3261355 · 12.5 mo to decide | 12.9 | Application Refused | 2022-10-27 |
Upper Ogmore Wind Farm RES UK & Ireland Limited · DNS/3213662 · 22.6 mo to decide | 25.2 | Awaiting Construction | 2022-09-22 |
Does Welsh Government (NSIP) approve onshore wind schemes?
Yes — of the 12 onshore wind schemes Welsh Government (NSIP) has decided, 67% were approved (8 granted, 4 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in Welsh Government (NSIP)?
The median time from application to decision is 15.1 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Welsh Government (NSIP) consented?
369 MW has been consented across 8 approved schemes, with 188 MW refused. A further 8 applications awaits a decision.
Other technologies in Welsh Government (NSIP)
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.