Novarly ParcelRenewable sites

Renewable sitesLodge Farm 1

Lodge Farm 1

Lodge Farm 1 is an operational 1 MW onshore wind farm in Pembrokeshire, generating since 1 August 2006. Planning permission was granted on 1 October 2005, 9 months after submission. Operator of record: Private Developer.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2006
Wind Onshore
Technology
Private Developer
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted7 January 2005
Permission granted1 October 2005
9 months after submission
Operational1 August 2006
10 months after consent

Screening a site of your own?

RedlineUK · £39

Pembrokeshire approves 47% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lodge Farm 1’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Pembrokeshire’s record on onshore wind

Pembrokeshire has decided 15 onshore wind schemes and approved 47%, taking a median of 8 months. See every onshore wind scheme decision in Pembrokeshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
51.5 km
Solar Photovoltaics · Operational
242.9 km
Wind Onshore · Operational
3.23.4 km
Solar Photovoltaics · Operational
9.94.7 km
Solar Photovoltaics · Operational
0.54.8 km
Wind Onshore · Operational
8.25.2 km
Wind Onshore · Under Construction
14.45.3 km
Wind Onshore · Operational
1.66.8 km

How big is Lodge Farm 1?

Lodge Farm 1 has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lodge Farm 1?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lodge Farm 1 approved and built?

The application was submitted on 7 January 2005. Permission was granted on 1 October 2005, 9 months later. The site became operational on 1 August 2006, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3272.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode