Lodge Farm 1
Lodge Farm 1 is operational in Pembrokeshire with a recorded capacity of 1 MW, and has been generating since 2006-08-01.
Planning and build timeline
| Application submitted | 2005-01-07 |
| Permission granted | 2005-10-01 9 months after submission |
| Operational | 2006-08-01 10 months after consent |
Pembrokeshire’s record on onshore wind
Pembrokeshire has decided 15 onshore wind schemes and approved 47%, taking a median of 8 months. See every onshore wind scheme decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Liddeston Ridge Solar Park (Milford Haven) Solar Photovoltaics · Operational | 5 | 1.5 km |
Tiers Cross Solar Farm Solar Photovoltaics · Operational | 24 | 2.9 km |
Castle Pill - Repowering Wind Onshore · Operational | 3.2 | 3.4 km |
Dragon Long Meadow - Solar farm Solar Photovoltaics · Operational | 9.9 | 4.7 km |
Bolton Hill WTW Solar Photovoltaics · Operational | 0.5 | 4.8 km |
Wear Point Wind Onshore · Operational | 8.2 | 5.2 km |
Dragon Energy Park - Wind Farm Wind Onshore · Under Construction | 14.4 | 5.3 km |
Lawrence Landfill Wind Onshore · Operational | 1.6 | 6.8 km |
How big is Lodge Farm 1?
Lodge Farm 1 has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lodge Farm 1?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lodge Farm 1 approved and built?
The application was submitted on 2005-01-07. Permission was granted on 2005-10-01, 9 months later. The site became operational on 2006-08-01, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3272.