Renewable planning › Onshore wind › Pembrokeshire
Onshore wind planning in Pembrokeshire
Pembrokeshire has decided 15 onshore wind schemes and approved 47% of them, taking a median of 8 months to decide. Consented capacity: 16 MW. 3 applications still awaiting a decision.
How Pembrokeshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, Pembrokeshire sits in the 16th percentile for approval rate (21 points below the England average) and the 85th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (19)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Newhouse Farm, Canaston Bridge - Wind Turbines Slebech Investment Limited · 25/0196/PA | 3 | Application Withdrawn | 2025-06-30 |
Trebover Farm - Wind Turbine Abergwaun Community Turbine · 24/0745/PA · 6.3 mo to decide | 0.23 | Awaiting Construction | 2025-05-22 |
Summerton Farm, Sageston - Wind Turbine Constantine Wind Energy Limited · 25/0118/PA | — | Application Submitted | 2025-05-08 |
Summerton Farm, Sageston - Wind Turbine Constantine Wind Energy Limited · 23/0723/PA · 3.4 mo to decide | 0.33 | Application Refused | 2024-03-11 |
Rhos-Hill, Cilgerran - Wind Turbine Infinite Renwables Limited · 23/0479/PA | 0.6 | Application Submitted | 2023-08-25 |
Pensygwarne, Croesgoch - Wind Turbine Y Draig Goch Energy Limited · 21/0993/PA · 9.1 mo to decide | 0.22 | Awaiting Construction | 2022-09-28 |
Rhoscrowther Wind Farm Njord Energy · 13/0876/PA · 11.7 mo to decide | 11.5 | Revised | 2015-01-21 |
Lawrence Landfill Wind Energy Direct · 12/1206/PA · 16.5 mo to decide | 1.6 | Operational | 2014-08-26 |
MELIN, Pen Y Bank Private Developer · 12/1100/PA · 7.1 mo to decide | 1 | Application Refused | 2013-10-02 |
Princes Gate Spring Water Princes Gate Spring Water · 11/0712/PA · 19.7 mo to decide | 1.6 | Operational | 2013-07-09 |
Wear Point John Laing Environmental Assets Group · 09/0544/PA · 7.7 mo to decide | 8.2 | Operational | 2010-05-25 |
Castle Pill - Repowering John Laing Environmental Assets Group · 05/0394/PA · 5.9 mo to decide | 3.2 | Operational | 2005-12-19 |
Lodge Farm 1 Private Developer · 04/1243/PA · 8.8 mo to decide | 1 | Operational | 2005-10-01 |
Jordanston Wind Farm RWE npower · 97/520 · 47 mo to decide | 9.8 | Application Refused | 2001-09-01 |
Rhoscrowther Wind Cluster THREE WAY WIND LTD/ TXU Europower Ltd · 16.4 mo to decide | 2.2 | Application Refused | 2001-04-12 |
Cilciffeth 'B' Wind Farm South Wales Power / SWALEC / National Windpower · 8 mo to decide | 7.8 | Application Refused | 1999-10-01 |
Cilciffeth 'A' Wind Farm South Wales Power / SWALEC / National Windpower · 8 mo to decide | 7.8 | Application Refused | 1999-10-01 |
Trenewydd Wind Farm RWE npower · 8 mo to decide | 6.3 | Application Refused | 1999-10-01 |
Corston Windfarm NOVERA / Renewable Energy Systems (RES) · 5 mo to decide | 7.9 | Application Refused | 1996-03-05 |
Does Pembrokeshire approve onshore wind schemes?
Yes — of the 15 onshore wind schemes Pembrokeshire has decided, 47% were approved (7 granted, 8 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in Pembrokeshire?
The median time from application to decision is 8 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Pembrokeshire consented?
16 MW has been consented across 7 approved schemes, with 43 MW refused. A further 3 applications awaits a decision.
Other technologies in Pembrokeshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.