Renewable sites › Loicher Lane
Loicher Lane
Loicher Lane is an operational 8 MW biomass plant in Sheffield, generating since 21 March 2016. Planning permission was granted on 26 May 2011, 20 months after submission. Operator of record: Rocpower.
Planning and build timeline
| Application submitted | 22 September 2009 |
| Permission granted | 26 May 2011 20 months after submission |
| Operational | 21 March 2016 58 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Sheffield: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Loicher Lane’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 1.1 | 3.6 km |
Biomass (dedicated) · Operational | 30 | 4.5 km |
Battery · Operational | 10 | 4.5 km |
Landfill Gas · Operational | 1.2 | 4.8 km |
Biomass (dedicated) · Operational | 42 | 5.8 km |
EfW Incineration · Operational | 19.3 | 6.4 km |
Wind Onshore · Operational | 2.6 | 8 km |
Battery · Operational | 0.3 | 10.1 km |
How big is Loicher Lane?
Loicher Lane has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Loicher Lane?
REPD records the operator as Rocpower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Loicher Lane approved and built?
The application was submitted on 22 September 2009. Permission was granted on 26 May 2011, 20 months later. The site became operational on 21 March 2016, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6274.