Sheffield ERF
Sheffield ERF is operational in Sheffield with a recorded capacity of 19.3 MW, and has been generating since 1999-03-31.
Planning and build timeline
| Application submitted | 1996-01-16 |
| Permission granted | 1996-03-07 2 months after submission |
| Operational | 1999-03-31 37 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Parkwood Landfill Scheme Landfill Gas · Operational | 1.2 | 2.8 km |
Advanced Manufacturing Research Centre Wind Onshore · Operational | 2.6 | 4.7 km |
Blackburn Meadows Biomass Plant Biomass (dedicated) · Operational | 30 | 5 km |
Blackburn Meadows Battery · Operational | 10 | 5 km |
Meadow Hall Power Landfill Gas · Operational | 1.1 | 5.2 km |
Templeborough Biomass Power Plant- Rotherham Biomass (dedicated) · Operational | 42 | 6.4 km |
Loicher Lane Biomass (dedicated) · Operational | 8 | 6.4 km |
Holbrook Community Renewable Energy Centre Biomass (dedicated) · Operational | 6.5 | 9.9 km |
How big is Sheffield ERF?
Sheffield ERF has a recorded installed capacity of 19.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Sheffield ERF?
REPD records the operator as Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Sheffield ERF approved and built?
The application was submitted on 1996-01-16. Permission was granted on 1996-03-07, 2 months later. The site became operational on 1999-03-31, 37 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 903.