Novarly ParcelRenewable sites

Renewable sitesChapel Hill

Chapel Hill

Chapel Hill is operational in Pembrokeshire with a recorded capacity of 8 MW, and has been generating since 2015-03-27.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-27
Solar Photovoltaics
Technology
Wessex Solar Energy
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted2014-05-14
Permission granted2014-07-29
2 months after submission
Operational2015-03-27
8 months after consent

Pembrokeshire’s record on solar

Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire

Other built sites within 15 km

SiteMWDistance
Hoplass Farm
Solar Photovoltaics · Operational
105.4 km
Golden Hill
Solar Photovoltaics · Operational
6.25.5 km
Wogaston Solar Farm
Solar Photovoltaics · Operational
5.35.8 km
West Farm, Cosheston - Solar Farm
Solar Photovoltaics · Under Construction
97 km
West Farm (Solar)
Solar Photovoltaics · Operational
7.77.1 km
Wear Point
Wind Onshore · Operational
8.27.4 km
Dragon Long Meadow - Solar farm
Solar Photovoltaics · Operational
9.97.8 km
Dragon Energy Park - Wind Farm
Wind Onshore · Under Construction
14.48.2 km

How big is Chapel Hill?

Chapel Hill has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Chapel Hill?

REPD records the operator as Wessex Solar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Chapel Hill approved and built?

The application was submitted on 2014-05-14. Permission was granted on 2014-07-29, 2 months later. The site became operational on 2015-03-27, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2326.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council