Renewable sites › Wishaw Battery Storage Facility
Wishaw Battery Storage Facility
Wishaw Battery Storage Facility is an operational 49.99 MW battery storage site in North Lanarkshire, generating since 15 November 2023. Planning permission was granted on 25 November 2020, 2 months after submission. Operator of record: Zenobe Energy.
Planning and build timeline
| Application submitted | 24 September 2020 |
| Permission granted | 25 November 2020 2 months after submission |
| Operational | 15 November 2023 36 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in North Lanarkshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Wishaw Battery Storage Facility’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Biomass (dedicated) · Operational | 17 | 3.5 km |
Landfill Gas · Operational | 2.3 | 5.1 km |
Landfill Gas · Operational | 1.9 | 5.1 km |
Wind Onshore · Operational | 2.2 | 5.1 km |
Wind Onshore · Operational | 8.4 | 6 km |
Small Hydro · Operational | — | 7.8 km |
Wind Onshore · Operational | 6 | 8.6 km |
Advanced Conversion Technologies · Under Construction | 25 | 9.1 km |
How big is Wishaw Battery Storage Facility?
Wishaw Battery Storage Facility has a recorded installed capacity of 49.99 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wishaw Battery Storage Facility?
REPD records the operator as Zenobe Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wishaw Battery Storage Facility approved and built?
The application was submitted on 24 September 2020. Permission was granted on 25 November 2020, 2 months later. The site became operational on 15 November 2023, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9522.
Novarly Parcel · official public data, read properly · parcel.novarly.com