Novarly ParcelRenewable sites

Renewable sitesLochhead Farm

Lochhead Farm

Lochhead Farm is operational in South Lanarkshire with a recorded capacity of 6 MW, and has been generating since 2009-07-01.

6 MW
Capacity
as recorded in REPD
Operational
Status
since 2009-07-01
Wind Onshore
Technology
A7 Energy / Green Energy
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted2005-04-01
Permission granted2006-05-01
13 months after submission
Operational2009-07-01
38 months after consent

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Marshill Farm
Wind Onshore · Operational
1.53.2 km
The Rosti Factory
Wind Onshore · Operational
2.23.5 km
LADEHEAD FARM - WIND TURBINES
Wind Onshore · Operational
2.46.4 km
Kype Muir Wind Farm
Wind Onshore · Operational
88.47.8 km
Kype Muir Wind Farm Extension
Wind Onshore · Operational
67.27.8 km
Auchrobert Wind Farm
Wind Onshore · Operational
368 km
Strathaven Airfield
Solar Photovoltaics · Operational
8.2 km
Woodlands Wind Farm
Wind Onshore · Operational
2.68.3 km

How big is Lochhead Farm?

Lochhead Farm has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lochhead Farm?

REPD records the operator as A7 Energy / Green Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lochhead Farm approved and built?

The application was submitted on 2005-04-01. Permission was granted on 2006-05-01, 13 months later. The site became operational on 2009-07-01, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3453.

Novarly Parcel · official public data, read properly · parcel.novarly.com