Lochhead Farm

Lochhead Farm is an operational 6 MW onshore wind farm in South Lanarkshire, generating since 1 July 2009. Planning permission was granted on 1 May 2006, 13 months after submission. Operator of record: A7 Energy / Green Energy.

6 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2009
Wind Onshore
Technology
A7 Energy / Green Energy
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted1 April 2005
Permission granted1 May 2006
13 months after submission
Operational1 July 2009
38 months after consent

Screening a site of your own?

RedlineUK · £39

South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Lochhead Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
1.53.2 km
Wind Onshore · Operational
2.23.5 km
Wind Onshore · Operational
2.46.4 km
Wind Onshore · Operational
88.47.8 km
Wind Onshore · Operational
67.27.8 km
Wind Onshore · Operational
368 km
Solar Photovoltaics · Operational
8.2 km
Wind Onshore · Operational
2.68.3 km

How big is Lochhead Farm?

Lochhead Farm has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lochhead Farm?

REPD records the operator as A7 Energy / Green Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lochhead Farm approved and built?

The application was submitted on 1 April 2005. Permission was granted on 1 May 2006, 13 months later. The site became operational on 1 July 2009, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3453.