Renewable sites › Liberty Steel Dalzell
Liberty Steel Dalzell
Liberty Steel Dalzell is an operational 17 MW biomass plant in North Lanarkshire, generating since 30 March 2017. REPD does not record the planning grant date. Operator of record: SIMEC/ Liberty House.
Planning and build timeline
| Application submitted | not recorded |
| Permission granted | not recorded |
| Operational | 30 March 2017 |
Screening a site of your own?
Redline runs the record on your own boundary in North Lanarkshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Liberty Steel Dalzell’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | 49.99 | 3.5 km |
Landfill Gas · Operational | 1.9 | 4 km |
Small Hydro · Operational | — | 4.6 km |
Landfill Gas · Operational | 2.3 | 5.7 km |
Advanced Conversion Technologies · Under Construction | 25 | 6 km |
Wind Onshore · Operational | 2.2 | 7.2 km |
Solar Photovoltaics · Operational | 0.2 | 7.5 km |
Wind Onshore · Operational | 2.5 | 7.9 km |
How big is Liberty Steel Dalzell?
Liberty Steel Dalzell has a recorded installed capacity of 17 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Liberty Steel Dalzell?
REPD records the operator as SIMEC/ Liberty House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Liberty Steel Dalzell approved and built?
REPD does not record a submission date. REPD does not record a grant date. The site became operational on 30 March 2017.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6731.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode