Renewable sites › Greengairs Landfill Scheme Phase I
Greengairs Landfill Scheme Phase I
Greengairs Landfill Scheme Phase I is operational in North Lanarkshire with a recorded capacity of 1.9 MW, and has been generating since 1996-05-01.
Planning and build timeline
| Application submitted | 1994-02-25 |
| Permission granted | 1994-05-24 3 months after submission |
| Operational | 1996-05-01 23 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Auchinlea Landfill Site Landfill Gas · Operational | 2.3 | 2.6 km |
Liberty Steel Dalzell Biomass (dedicated) · Operational | 17 | 4 km |
Damhead Farm Wind Onshore · Operational | 2.5 | 4.3 km |
Coatbridge Material Recovery and Renewable Energy Facility Advanced Conversion Technologies · Under Construction | 25 | 5.1 km |
Wishaw Battery Storage Facility Battery · Operational | 49.99 | 5.1 km |
Henry Colbeck Office Solar Photovoltaics · Operational | 0.2 | 6.3 km |
Hamilton Waste Water Treatment Works - Hydro Scheme Small Hydro · Operational | — | 7.5 km |
Watsonhead Wind Farm Wind Onshore · Operational | 8.4 | 7.6 km |
How big is Greengairs Landfill Scheme Phase I?
Greengairs Landfill Scheme Phase I has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Greengairs Landfill Scheme Phase I?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Greengairs Landfill Scheme Phase I approved and built?
The application was submitted on 1994-02-25. Permission was granted on 1994-05-24, 3 months later. The site became operational on 1996-05-01, 23 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 694.