Watsonhead Wind Farm

Watsonhead Wind Farm is an operational 8.4 MW onshore wind farm in North Lanarkshire, generating since 1 October 2023. Planning permission was granted on 24 February 2020, 24 months after submission. Operator of record: Green Cat Renewables.

8.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 October 2023
Wind Onshore
Technology
Green Cat Renewables
North Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted21 February 2018
Permission granted24 February 2020
24 months after submission
Operational1 October 2023
43 months after consent

Screening a site of your own?

RedlineUK · £39

North Lanarkshire approves 70% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Watsonhead Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

North Lanarkshire’s record on onshore wind

North Lanarkshire has decided 20 onshore wind schemes and approved 70%, taking a median of 16.8 months. See every onshore wind scheme decision in North Lanarkshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
0.234.9 km
Landfill Gas · Operational
2.35.3 km
Wind Onshore · Operational
48.45.3 km
Wind Onshore · Operational
1245.3 km
Wind Onshore · Operational
155.3 km
Battery · Operational
49.996 km
Landfill Gas · Operational
1.97.6 km
Wind Onshore · Under Construction
8.48.4 km

How big is Watsonhead Wind Farm?

Watsonhead Wind Farm has a recorded installed capacity of 8.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Watsonhead Wind Farm?

REPD records the operator as Green Cat Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Watsonhead Wind Farm approved and built?

The application was submitted on 21 February 2018. Permission was granted on 24 February 2020, 24 months later. The site became operational on 1 October 2023, 43 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 15144.