The Rosti Factory
The Rosti Factory is an operational 2.2 MW onshore wind farm in South Lanarkshire, generating since 18 February 2013. Planning permission was granted on 24 November 2010, 19 months after submission. Operator of record: Branna Industrial & Technical Services Ltd.
Planning and build timeline
| Application submitted | 21 April 2009 |
| Permission granted | 24 November 2010 19 months after submission |
| Operational | 18 February 2013 27 months after consent |
Screening a site of your own?
South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with The Rosti Factory’s recorded coordinate — swap in your own postcode or coordinates.
South Lanarkshire’s record on onshore wind
South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 6 | 3.5 km |
Wind Onshore · Operational | 1.5 | 4.5 km |
Battery · Operational | 49.99 | 5.1 km |
Biomass (dedicated) · Operational | 17 | 7.2 km |
Wind Onshore · Operational | 9 | 8.3 km |
Wind Onshore · Operational | 7.5 | 8.3 km |
Wind Onshore · Operational | 2.4 | 8.7 km |
Wind Onshore · Operational | 8.4 | 9.2 km |
How big is The Rosti Factory?
The Rosti Factory has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates The Rosti Factory?
REPD records the operator as Branna Industrial & Technical Services Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was The Rosti Factory approved and built?
The application was submitted on 21 April 2009. Permission was granted on 24 November 2010, 19 months later. The site became operational on 18 February 2013, 27 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3667.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode