Renewable sites › Computacenter Warehouse
Computacenter Warehouse
Computacenter Warehouse is under construction in Welwyn Hatfield with a recorded capacity of 2 MW.
Planning and build timeline
| Application submitted | 2019-01-29 |
| Permission granted | 2019-03-08 1 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Welwyn Hatfield’s record on solar
Welwyn Hatfield has decided 7 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Welwyn Hatfield →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tollgate Farm Battery Storage Battery · Under Construction | 49.5 | 4.4 km |
Coursers Farm AD Plant (Waste AD) Anaerobic Digestion · Operational | 3 | 5.3 km |
Aylett Nurseries - Solar Panels Solar Photovoltaics · Operational | — | 6.6 km |
Potters Bar Solar Farm Solar Photovoltaics · Operational | 5 | 7.8 km |
Land At Swanland Road Solar Photovoltaics · Operational | 5 | 8.8 km |
Blanche Lane, South Mimms - Solar Panels Solar Photovoltaics · Under Construction | 0.61 | 9.5 km |
Land North of Chiltern Greeen Solar Photovoltaics · Operational | 5 | 12.2 km |
Cattlegate Farm Biogas (Farm AD) Anaerobic Digestion · Operational | 1.5 | 12.7 km |
How big is Computacenter Warehouse?
Computacenter Warehouse has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Computacenter Warehouse?
REPD records the operator as Computacenter UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Computacenter Warehouse approved and built?
The application was submitted on 2019-01-29. Permission was granted on 2019-03-08, 1 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7290.