Ratty's Lane Sustainable Energy Facility (Waste AD) is an operational 3 MW anaerobic digestion plant in Broxbourne, generating since 4 July 2016. Planning permission was granted on 26 March 2012, 21 months after submission. Operator of record: Biogen (formerly Tamar Energy).
Planning and build timeline
| Application submitted | 28 June 2010 |
| Permission granted | 26 March 2012 21 months after submission |
| Operational | 4 July 2016 51 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Broxbourne: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Ratty's Lane Sustainable Energy Facility (Waste AD)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Advanced Conversion Technologies · Under Construction | 9.6 | 0 km |
Anaerobic Digestion · Operational | 2.3 | 1.4 km |
Landfill Gas · Operational | 3.9 | 6.7 km |
Landfill Gas · Operational | 2.6 | 7.3 km |
Solar Photovoltaics · Operational | 1.8 | 9.8 km |
Anaerobic Digestion · Operational | 1.2 | 10.8 km |
Anaerobic Digestion · Operational | 1.5 | 11.1 km |
Solar Photovoltaics · Under Construction | 0.2 | 12.3 km |
How big is Ratty's Lane Sustainable Energy Facility (Waste AD)?
Ratty's Lane Sustainable Energy Facility (Waste AD) has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ratty's Lane Sustainable Energy Facility (Waste AD)?
REPD records the operator as Biogen (formerly Tamar Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ratty's Lane Sustainable Energy Facility (Waste AD) approved and built?
The application was submitted on 28 June 2010. Permission was granted on 26 March 2012, 21 months later. The site became operational on 4 July 2016, 51 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 311.