Novarly ParcelRenewable sites

Renewable sitesTwin Tumps Way - Solar Panels

Twin Tumps Way - Solar Panels

Twin Tumps Way - Solar Panels is operational in Greenwich with a recorded capacity of 0.62 MW, and has been generating since 2022-05-28.

0.62 MW
Capacity
as recorded in REPD
Operational
Status
since 2022-05-28
Solar Photovoltaics
Technology
WM Morrisons Supermarkets Plc
Greenwich
Authority
England

Planning and build timeline

Application submitted2022-02-22
Permission granted2022-12-15
10 months after submission
Operational2022-05-28

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Greenwich’s record on solar

Greenwich has decided 13 solar farms and approved 54%, taking a median of 1.8 months. See every solar farm decision in Greenwich

Other built sites within 15 km

SiteMWDistance
Beckton STW Biodiesel Power Plant
Biomass (dedicated) · Operational
81.5 km
Beckton Gas Pressure Reduction Station
Biomass (dedicated) · Operational
191.7 km
Crossness Sewage Works PV
Solar Photovoltaics · Operational
1.52.4 km
Beckton Sewage Treatment Works
Wind Onshore · Operational
2.22.7 km
Beckton STW Enhanced Sludge Digestion
Sewage Sludge Digestion · Operational
5.82.7 km
Crossness Sewage Works Turbine
Wind Onshore · Operational
2.52.7 km
Crossness Sewage Works
Sewage Sludge Digestion · Operational
5.72.7 km
East Dagenham Docks AD (AD)
Anaerobic Digestion · Operational
1.42.9 km

How big is Twin Tumps Way - Solar Panels?

Twin Tumps Way - Solar Panels has a recorded installed capacity of 0.62 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Twin Tumps Way - Solar Panels?

REPD records the operator as WM Morrisons Supermarkets Plc. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Twin Tumps Way - Solar Panels approved and built?

The application was submitted on 2022-02-22. Permission was granted on 2022-12-15, 10 months later. The site became operational on 2022-05-28.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10758.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council