Renewable sites › Beckton Gas Pressure Reduction Station
Beckton Gas Pressure Reduction Station
Beckton Gas Pressure Reduction Station is an operational 19 MW biomass plant in Newham, generating since 30 March 2015. Planning permission was granted on 26 August 2010, 7 months after submission. Operator of record: Icon, EEA Holdings & 2OC consortium.
Planning and build timeline
| Application submitted | 15 January 2010 |
| Permission granted | 26 August 2010 7 months after submission |
| Operational | 30 March 2015 55 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Newham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Beckton Gas Pressure Reduction Station’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Biomass (dedicated) · Operational | 8 | 0.3 km |
Wind Onshore · Operational | 2.2 | 1 km |
Sewage Sludge Digestion · Operational | 5.8 | 1 km |
Solar Photovoltaics · Under Construction | 0.22 | 1.4 km |
Solar Photovoltaics · Operational | 0.62 | 1.7 km |
Anaerobic Digestion · Operational | 1.4 | 3.4 km |
Anaerobic Digestion · Operational | 1.4 | 3.4 km |
Solar Photovoltaics · Under Construction | 0.24 | 3.6 km |
How big is Beckton Gas Pressure Reduction Station?
Beckton Gas Pressure Reduction Station has a recorded installed capacity of 19 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Beckton Gas Pressure Reduction Station?
REPD records the operator as Icon, EEA Holdings & 2OC consortium. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Beckton Gas Pressure Reduction Station approved and built?
The application was submitted on 15 January 2010. Permission was granted on 26 August 2010, 7 months later. The site became operational on 30 March 2015, 55 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 143.
Novarly Parcel · official public data, read properly · parcel.novarly.com