Renewable sites › East Dagenham Docks AD (AD)
East Dagenham Docks AD (AD)
East Dagenham Docks AD (AD) is an operational 1.4 MW anaerobic digestion plant in Barking and Dagenham, generating since 4 March 2014. Planning permission was granted on 16 March 2012, 9 months after submission. Operator of record: Lynton Development / Teg Environmental.
Planning and build timeline
| Application submitted | 8 June 2011 |
| Permission granted | 16 March 2012 9 months after submission |
| Operational | 4 March 2014 24 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Barking and Dagenham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with East Dagenham Docks AD (AD)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Operational | 1.4 | 0.3 km |
Wind Onshore · Operational | 5.9 | 1 km |
Wind Onshore · Operational | 2 | 1.2 km |
Solar Photovoltaics · Operational | 1.5 | 1.5 km |
Wind Onshore · Operational | 2.5 | 2.1 km |
Sewage Sludge Digestion · Operational | 5.7 | 2.1 km |
Battery · Under Construction | 2.5 | 2.2 km |
Solar Photovoltaics · Operational | 0.62 | 2.9 km |
How big is East Dagenham Docks AD (AD)?
East Dagenham Docks AD (AD) has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates East Dagenham Docks AD (AD)?
REPD records the operator as Lynton Development / Teg Environmental. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was East Dagenham Docks AD (AD) approved and built?
The application was submitted on 8 June 2011. Permission was granted on 16 March 2012, 9 months later. The site became operational on 4 March 2014, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 281.