Gelliargwellt Uchaf Farm AD
Gelliargwellt Uchaf Farm AD is an operational 1.4 MW anaerobic digestion plant in Caerphilly, generating since 1 February 2016. Planning permission was granted on 8 December 2011, 9 months after submission. Operator of record: Bryn Group.
Planning and build timeline
| Application submitted | 23 March 2011 |
| Permission granted | 8 December 2011 9 months after submission |
| Operational | 1 February 2016 50 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Caerphilly: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Gelliargwellt Uchaf Farm AD’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 13.4 | 1.2 km |
Solar Photovoltaics · Operational | 2.6 | 6.7 km |
Wind Onshore · Operational | 4 | 7.2 km |
Solar Photovoltaics · Operational | 4.1 | 7.6 km |
Solar Photovoltaics · Operational | 10 | 7.6 km |
Solar Photovoltaics · Operational | 4.7 | 7.8 km |
Solar Photovoltaics · Operational | 4.9 | 8.1 km |
Solar Photovoltaics · Operational | 8.5 | 8.5 km |
How big is Gelliargwellt Uchaf Farm AD?
Gelliargwellt Uchaf Farm AD has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gelliargwellt Uchaf Farm AD?
REPD records the operator as Bryn Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gelliargwellt Uchaf Farm AD approved and built?
The application was submitted on 23 March 2011. Permission was granted on 8 December 2011, 9 months later. The site became operational on 1 February 2016, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6450.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode