LADEHEAD FARM - WIND TURBINES is operational in South Lanarkshire with a recorded capacity of 2.4 MW, and has been generating since 2016-09-15.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-09-15
Wind Onshore
Technology
PI Renewables 2 Ltd
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted2012-10-19
Permission granted2015-01-22
27 months after submission
Operational2016-09-15
20 months after consent

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Woodlands Wind Farm
Wind Onshore · Operational
2.61.9 km
Marshill Farm
Wind Onshore · Operational
1.54.3 km
Auchrobert Wind Farm
Wind Onshore · Operational
364.8 km
Nutberry Wind Farm
Wind Onshore · Operational
155.6 km
Cumberhead West Wind Farm
Wind Onshore · Under Construction
1266 km
Cumberhead West Wind Farm
Battery · Under Construction
406 km
Coalburn Energy - Battery Storage
Battery · Under Construction
5006.3 km
Lochhead Farm
Wind Onshore · Operational
66.4 km

How big is LADEHEAD FARM - WIND TURBINES?

LADEHEAD FARM - WIND TURBINES has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates LADEHEAD FARM - WIND TURBINES?

REPD records the operator as PI Renewables 2 Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was LADEHEAD FARM - WIND TURBINES approved and built?

The application was submitted on 2012-10-19. Permission was granted on 2015-01-22, 27 months later. The site became operational on 2016-09-15, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3915.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council