Novarly ParcelRenewable sites

Renewable sitesLADEHEAD FARM - WIND TURBINES

LADEHEAD FARM - WIND TURBINES

LADEHEAD FARM - WIND TURBINES is an operational 2.4 MW onshore wind farm in South Lanarkshire, generating since 15 September 2016. Planning permission was granted on 22 January 2015, 27 months after submission. Operator of record: PI Renewables 2 Ltd.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 15 September 2016
Wind Onshore
Technology
PI Renewables 2 Ltd
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted19 October 2012
Permission granted22 January 2015
27 months after submission
Operational15 September 2016
20 months after consent

Screening a site of your own?

RedlineUK · £39

South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with LADEHEAD FARM - WIND TURBINES’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.61.9 km
Wind Onshore · Operational
1.54.3 km
Wind Onshore · Operational
364.8 km
Wind Onshore · Operational
155.6 km
Battery · Under Construction
406 km
Wind Onshore · Under Construction
1266 km
Battery · Under Construction
5006.3 km
Wind Onshore · Operational
66.4 km

How big is LADEHEAD FARM - WIND TURBINES?

LADEHEAD FARM - WIND TURBINES has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates LADEHEAD FARM - WIND TURBINES?

REPD records the operator as PI Renewables 2 Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was LADEHEAD FARM - WIND TURBINES approved and built?

The application was submitted on 19 October 2012. Permission was granted on 22 January 2015, 27 months later. The site became operational on 15 September 2016, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3915.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode