Renewable sites › Blantyre Muir Wind Farm
Blantyre Muir Wind Farm
Blantyre Muir Wind Farm is operational in South Lanarkshire with a recorded capacity of 9 MW, and has been generating since 2013-12-30.
Planning and build timeline
| Application submitted | 2007-08-16 |
| Permission granted | 2009-11-03 27 months after submission |
| Operational | 2013-12-30 50 months after consent |
South Lanarkshire’s record on onshore wind
South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Blantyre Muir Wind Farm extension Wind Onshore · Operational | 7.5 | 0 km |
Allers Wastewater Treatment Works, Barrie Road - Solar Pv Array Solar Photovoltaics · Operational | 0.24 | 5.1 km |
Hamilton Waste Water Treatment Works - Hydro Scheme Small Hydro · Operational | — | 6.3 km |
Strathaven Airfield Solar Photovoltaics · Operational | — | 7.1 km |
Whitelee Wind Farm Battery Storage Extension Battery · Operational | 50 | 7.2 km |
Tennant Avenue College, East Kilbride - Solar Panels Solar Photovoltaics · Under Construction | 0.94 | 8.3 km |
The Rosti Factory Wind Onshore · Operational | 2.2 | 8.3 km |
Lochhead Farm Wind Onshore · Operational | 6 | 8.5 km |
How big is Blantyre Muir Wind Farm?
Blantyre Muir Wind Farm has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Blantyre Muir Wind Farm?
REPD records the operator as Blantyre Muir Wind Energy Ltd�. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Blantyre Muir Wind Farm approved and built?
The application was submitted on 2007-08-16. Permission was granted on 2009-11-03, 27 months later. The site became operational on 2013-12-30, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3810.
Novarly Parcel · official public data, read properly · parcel.novarly.com