Renewable sites › Blantyre Muir Wind Farm
Blantyre Muir Wind Farm
Blantyre Muir Wind Farm is an operational 9 MW onshore wind farm in South Lanarkshire, generating since 30 December 2013. Planning permission was granted on 3 November 2009, 27 months after submission. Operator of record: Blantyre Muir Wind Energy Ltd�.
Planning and build timeline
| Application submitted | 16 August 2007 |
| Permission granted | 3 November 2009 27 months after submission |
| Operational | 30 December 2013 50 months after consent |
Screening a site of your own?
South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Blantyre Muir Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
South Lanarkshire’s record on onshore wind
South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 7.5 | 0 km |
Solar Photovoltaics · Operational | 0.24 | 5.1 km |
Small Hydro · Operational | — | 6.3 km |
Solar Photovoltaics · Operational | — | 7.1 km |
Battery · Operational | 50 | 7.2 km |
Solar Photovoltaics · Under Construction | 0.94 | 8.3 km |
Wind Onshore · Operational | 2.2 | 8.3 km |
Wind Onshore · Operational | 6 | 8.5 km |
How big is Blantyre Muir Wind Farm?
Blantyre Muir Wind Farm has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Blantyre Muir Wind Farm?
REPD records the operator as Blantyre Muir Wind Energy Ltd�. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Blantyre Muir Wind Farm approved and built?
The application was submitted on 16 August 2007. Permission was granted on 3 November 2009, 27 months later. The site became operational on 30 December 2013, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3810.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode