Renewable planning › Onshore wind › South Lanarkshire
Onshore wind planning in South Lanarkshire
South Lanarkshire has decided 49 onshore wind schemes and approved 73% of them, taking a median of 15.9 months to decide. Consented capacity: 584 MW. 12 applications still awaiting a decision.
How South Lanarkshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, South Lanarkshire sits in the 59th percentile for approval rate (5 points above the England average) and the 37th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (71)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Yonderton Farm, Lesmahagow - Wind Turbine ILI (Yonderton) Limited · P/24/0522 · 17.5 mo to decide | 0.95 | Application Refused | 2025-12-17 |
Dillars Hill, Dillars - Wind Turbines Constantine Wind Energy Limited · P/25/0254 | — | Application Withdrawn | 2025-06-24 |
Bankend Rig II Wind Farm Wilson Renewables II Llp · P/21/1385 · 46.6 mo to decide | 10.2 | Awaiting Construction | 2025-06-10 |
Woolfords Farm - Onshore Wind Turbines Woolffords Wind Energy Limited · P/22/0031 · 40.4 mo to decide | 19.8 | Awaiting Construction | 2025-05-30 |
East Merkland Farm, Sandford - Wind Turbines Clean Earth Energy Limited · P/23/1611 · 14.8 mo to decide | — | Application Refused | 2025-05-13 |
Auchtygemmel Farm, Muirhouse Road - Wind Turbines Constantine Wind Energy Limited · P/24/1444 · 4.6 mo to decide | — | Awaiting Construction | 2025-04-23 |
South Brownhill Farm, High Brownside - Wind Turbines Clean Earth Energy Limited · P/23/1610 · 11.4 mo to decide | — | Application Refused | 2025-02-28 |
Dungavel House, IRC Muirkirk Road - Wind Farm Clean Earth Energy Limited · P/22/1139 · 29.5 mo to decide | 11.4 | Awaiting Construction | 2025-01-22 |
Hawkwood Wind Farm, Kype Highway - Wind turbines Wilson Renewables IV Llp · P/24/1420 | 33 | Application Submitted | 2024-11-22 |
Little Gala Wind Farm BayWa r.e. UK Limited · P/22/0881 · 27.7 mo to decide | 30 | Appeal Withdrawn | 2024-09-30 |
Stoneyhill Farm Wind turbines Clean Earth · P/22/1259 | — | Application Withdrawn | 2024-06-03 |
Brae Wind Farm - 3 Wind turbines Private Developer · P/24/0700 | — | Application Submitted | 2024-06-03 |
Logoch Windfarm, East Kilbride - Wind turbine Constantine Wind Energy Limited · P/23/1040 · 7.2 mo to decide | 0.5 | Awaiting Construction | 2024-03-28 |
Mill Rig Wind Farm Banks Renewables · P/21/1127 · 32.8 mo to decide | 36 | Under Construction | 2024-03-20 |
Logoch Farm, Ardochrig Highway - Wind Turbine Constantine Wind Energy Limited · P/23/0576 | — | Revised | 2023-08-25 |
West Dykes Head - Wind turbines Cleanearth Energy · P/22/1610 | 7.6 | Application Submitted | 2023-01-12 |
Low Drumclog Farm, Drumclog - 3 Wind Turbines Clean Earth Energy Limited · P/22/0228 | 20 | Application Submitted | 2022-02-21 |
Priestgill Wind Farm Muirhall Energy · CL/17/0009 · 60.1 mo to decide | 46.2 | Under Construction | 2021-12-15 |
Cumberhead Wind Farm Octopus Renewables Infrastructure Trust · CL/15/0231 · 70.8 mo to decide | 48 | Operational | 2021-05-13 |
West Dykes CleanEarth · P/19/1829 · 12.4 mo to decide | 3 | Revised | 2020-12-29 |
Broken Cross (Former Surface Mine) BayWa r.e. UK Limited · P/19/1636 · 5.7 mo to decide | 48 | Operational | 2020-04-21 |
Poniel Wind Turbines 3R Energy (formerly Lantern Bidco) · CL/12/0043 | 9 | Application Withdrawn | 2020-03-24 |
Glentaggart Wind Farm Ventient (formerly Infinis) · CL/11/0461 | 17 | Appeal Withdrawn | 2020-02-14 |
High Blackwoodyards Farm HBY 2 · P/19/1712 | 2 | Appeal Refused | 2019-11-27 |
Draffanmarshill Farm T C Stewart and Sons Ltd · P/19/1258 | 4.2 | Application Submitted | 2019-09-10 |
South Priorhill Farm Muirhall Energy (Southrigg WT) · CL/15/0219 · 14.4 mo to decide | 1.5 | Planning Permission Expired | 2016-08-16 |
Stoney Hill Farm Private Developer · EK/15/0375 · 7.4 mo to decide | 2 | Planning Permission Expired | 2016-07-05 |
Kittymuir Farm West Coast Wind · HM/15/0336 · 10.1 mo to decide | 1.6 | Planning Permission Expired | 2016-06-27 |
Land associated with Rawhead Farm Raahead WT Limited · EK/14/0319 | 1.5 | Application Withdrawn | 2016-02-24 |
Land associated with Lairfad Lairfad WT Limited · EK/14/0320 | 1.5 | Application Withdrawn | 2016-02-24 |
Douglas West and Dalquhandy Renewable Energy Project Greencoat (formerly 3R Energy/Blue Energy) / BayWa r.e · CL/15/0273 · 6.6 mo to decide | 45 | Operational | 2016-02-02 |
Lion Hill Wind Farm (Crookedstane Farm 2) BayWa r.e. (formerly Forsa) · CL/13/0205 · 31.3 mo to decide | 11.4 | Planning Permission Expired | 2016-01-20 |
Crookedstane Farm BayWa r.e. (formerly Forsa) · CL/13/0206 · 31.2 mo to decide | 11.4 | Planning Permission Expired | 2016-01-19 |
Hill Rig Community Wind Farm Community Windpower · CL/15/0175 · 4.5 mo to decide | 28 | Application Refused | 2015-09-24 |
Muirhall South Muirhall Energy · CL/14/0113 · 15.7 mo to decide | 8.3 | Operational | 2015-07-10 |
Bankend Rig II Wind Farm Wilson Renewables II · EK/15/0217 | 10.2 | Revised | 2015-07-09 |
Bankend Wind Farm (extension) Wilson Renewables · EK/15/0217 | 10.2 | Revised | 2015-06-11 |
Hill Rig Community Windfarm Community Windpower · CL/14/0292 · 10.4 mo to decide | 28 | Revised | 2015-06-03 |
Halls Burn Stewart Energy Ltd · EK/14/0360 | 2.5 | Application Withdrawn | 2015-04-22 |
Leadhills Wind Farm Atmos · CL/13/0167 · 22.1 mo to decide | 49 | Application Refused | 2015-03-24 |
LADEHEAD FARM - WIND TURBINES PI Renewables 2 Ltd · CL/12/0461 · 27.1 mo to decide | 2.4 | Operational | 2015-01-22 |
Hazelside farm Mitchell Farming Partnerships (3R Energy) · CL/14/0132 · 8.6 mo to decide | 1.6 | Under Construction | 2014-12-18 |
Crutherland Farm Wind Turbine Renewable Energy Systems (RES) · EK/14/0111 · 6.5 mo to decide | 2 | Application Refused | 2014-11-07 |
Crofthill Wind Farm Banks Renewables · CL/13/0401 · 12.5 mo to decide | 17 | Application Refused | 2014-11-04 |
Andershaw Statkraft UK · CL/07/0454 · 83 mo to decide | 36 | Operational | 2014-06-09 |
Auchrobert Wind Farm Falck Renewables · CL/12/0556 · 15.8 mo to decide | 36 | Operational | 2014-04-09 |
Dykehead Farm wind turbine 3 Dykehead Renewables Ltd · EK/14/0014 | 2.3 | Application Withdrawn | 2014-04-01 |
Calla Wind Farm Willowind Developments · CL/12/0535 · 12.4 mo to decide | 18 | Application Refused | 2013-12-18 |
Marshill Farm Green Cat Renewables · CL/12/0300 · 17.3 mo to decide | 1.5 | Operational | 2013-12-18 |
Castlemilk and Carmunnock Community Windpark Trust Castlemilk and Carmunnock Community Windpark Trust · EK/13/0248 · 3.1 mo to decide | 2.5 | Application Refused | 2013-11-20 |
Woodlands Wind Farm WhiteRock Energy · CL/12/0139 · 16 mo to decide | 2.6 | Operational | 2013-07-22 |
Hazelside farm Mitchell Farming Partnerships (3R Energy) · CL/12/0493 | 2.4 | Revised | 2013-05-31 |
Muirhall Extension Muirhall Energy · CL/12/0074 · 6.6 mo to decide | 6.8 | Operational | 2012-09-10 |
West Browncastle Falck Renewables · EK/10/0358 · 20.9 mo to decide | 30 | Operational | 2012-07-09 |
Blantyre Muir Wind Farm extension West Coast Energy · HM/10/0478 · 19.7 mo to decide | 7.5 | Operational | 2012-05-25 |
Cartland Muir Wind Farm Energy4All · CL/11/0266 · 5.4 mo to decide | 5 | Application Refused | 2011-12-01 |
Calder Water Community Wind Farm Community Windpower (Community Wind Power) · EK/09/0290 · 27.1 mo to decide | 28 | Operational | 2011-11-29 |
Harrow's Law Scottish and Southern Energy (SSE) · CL/10/0095 · 15.7 mo to decide | 39 | Appeal Refused | 2011-06-27 |
Bankend Rig I & H Brown Ltd · EK/06/0311 · 60 mo to decide | 14.3 | Operational | 2011-06-16 |
Nutberry Wind Farm Renantis Falck Renewables Limited · CL/06/0662 · 54.2 mo to decide | 15 | Operational | 2011-04-05 |
The Rosti Factory Branna Industrial & Technical Services Ltd · HM/09/0173 · 19.1 mo to decide | 2.2 | Operational | 2010-11-24 |
Goodbush Hill Kenetech International · P/96/29 | 24 | Application Withdrawn | 2010-01-25 |
Dungavel Hill John Laing Environmental Assets Group · EK/06/0072 · 45.4 mo to decide | 29.9 | Operational | 2009-12-01 |
Blantyre Muir Wind Farm Blantyre Muir Wind Energy Ltd� · HM/07/0563 · 26.6 mo to decide | 9 | Operational | 2009-11-03 |
Muirhall Lomond Energy · CL/05/0209 · 42.4 mo to decide | 12.3 | Operational | 2008-10-10 |
Bogside A7 Energy · CL/05/0513 · 34.9 mo to decide | 2.3 | Application Refused | 2008-06-23 |
Lochhead Farm A7 Energy / Green Energy · HM/05/0147 · 13 mo to decide | 6 | Operational | 2006-05-01 |
Hagshaw Hill Wind Farm Extension Scottish Power Renewables · 11.6 mo to decide | 26 | Operational | 2005-12-28 |
Penbreck & Carmacoup Forest Private Developer · CI/01/0010 · 26 mo to decide | 27 | Revised | 2003-01-20 |
Hagshaw Hill Wind Farm Trigen · 5.7 mo to decide | 7.8 | Operational | 1994-11-02 |
Hagshaw Hill Wind Farm Trigen · 5.7 mo to decide | 7.8 | Operational | 1994-11-02 |
Does South Lanarkshire approve onshore wind schemes?
Yes — of the 49 onshore wind schemes South Lanarkshire has decided, 73% were approved (36 granted, 13 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in South Lanarkshire?
The median time from application to decision is 15.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has South Lanarkshire consented?
584 MW has been consented across 36 approved schemes, with 166 MW refused. A further 12 applications awaits a decision.
Other technologies in South Lanarkshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.