Renewable sites › Swansea University Bay Campus
Swansea University Bay Campus
Swansea University Bay Campus is operational in Neath Port Talbot with a recorded capacity of 0.2 MW, and has been generating since 2023-03-01.
Planning and build timeline
| Application submitted | 2020-06-22 |
| Permission granted | 2020-08-20 2 months after submission |
| Operational | 2023-03-01 30 months after consent |
Neath Port Talbot’s record on solar
Neath Port Talbot has decided 12 solar farms and approved 100%, taking a median of 5.7 months. See every solar farm decision in Neath Port Talbot →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Carn Nicholas Farm Solar Photovoltaics · Under Construction | 5 | 2.7 km |
Carn Nicholas Farm (Extension) Solar Photovoltaics · Operational | 10 | 2.7 km |
Baglan Bay Solar Farm - Phase 1 Solar Photovoltaics · Operational | 5 | 3.5 km |
Pioneer 2 - Hydrogen Production Facility Hydrogen · Under Construction | 2.5 | 4.1 km |
Briton / Neath Landfill Gas · Operational | 2.2 | 4.2 km |
Briton Ferry Landfill Gas · Operational | 2 | 4.2 km |
Pant-Y-Moch Farm Solar Photovoltaics · Operational | 5 | 8.1 km |
Brynwhilach Solar Park Solar Photovoltaics · Operational | 4 | 9.4 km |
How big is Swansea University Bay Campus?
Swansea University Bay Campus has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Swansea University Bay Campus?
REPD records the operator as Swansea University Estates. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Swansea University Bay Campus approved and built?
The application was submitted on 2020-06-22. Permission was granted on 2020-08-20, 2 months later. The site became operational on 2023-03-01, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8067.