Renewable sitesPant-Y-Moch Farm

Pant-Y-Moch Farm

Pant-Y-Moch Farm is an operational 5 MW solar farm in Neath Port Talbot, generating since 6 January 2016. Planning permission was granted on 31 October 2014, 4 months after submission. Operator of record: Canadian Solar.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 6 January 2016
Solar Photovoltaics
Technology
Canadian Solar
Neath Port Talbot
Authority
Wales

Planning and build timeline

Application submitted27 June 2014
Permission granted31 October 2014
4 months after submission
Operational6 January 2016
14 months after consent

Screening a site of your own?

RedlineUK · £39

Neath Port Talbot approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pant-Y-Moch Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Neath Port Talbot’s record on solar

Neath Port Talbot has decided 12 solar farms and approved 100%, taking a median of 5.7 months. See every solar farm decision in Neath Port Talbot

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
82.3 km
Biomass (dedicated) · Operational
143.6 km
Hydrogen · Under Construction
2.54 km
Wind Onshore · Operational
1.54.2 km
Biomass (dedicated) · Operational
404.2 km
Solar Photovoltaics · Operational
54.6 km
Landfill Gas · Operational
26.6 km
Landfill Gas · Operational
2.26.7 km

How big is Pant-Y-Moch Farm?

Pant-Y-Moch Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pant-Y-Moch Farm?

REPD records the operator as Canadian Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pant-Y-Moch Farm approved and built?

The application was submitted on 27 June 2014. Permission was granted on 31 October 2014, 4 months later. The site became operational on 6 January 2016, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1900.