Novarly ParcelRenewable sites

Renewable sitesCarn Nicholas Farm (Extension)

Carn Nicholas Farm (Extension)

Carn Nicholas Farm (Extension) is an operational 10 MW solar farm in Swansea, generating since 1 January 2023. Planning permission was granted on 17 March 2021, 14 months after submission. Operator of record: Innova Renewables Limited.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 1 January 2023
Solar Photovoltaics
Technology
Innova Renewables Limited
Swansea
Authority
Wales

Planning and build timeline

Application submitted31 January 2020
Permission granted17 March 2021
14 months after submission
Operational1 January 2023
22 months after consent

Screening a site of your own?

RedlineUK · £39

Swansea approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Carn Nicholas Farm (Extension)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Swansea’s record on solar

Swansea has decided 16 solar farms and approved 88%, taking a median of 4.5 months. See every solar farm decision in Swansea

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
50 km
Solar Photovoltaics · Operational
0.22.7 km
Landfill Gas · Operational
2.25.6 km
Landfill Gas · Operational
25.6 km
Solar Photovoltaics · Operational
56.2 km
Hydrogen · Under Construction
2.56.8 km
Solar Photovoltaics · Operational
46.9 km
Solar Photovoltaics · Operational
47.1 km

How big is Carn Nicholas Farm (Extension)?

Carn Nicholas Farm (Extension) has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Carn Nicholas Farm (Extension)?

REPD records the operator as Innova Renewables Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Carn Nicholas Farm (Extension) approved and built?

The application was submitted on 31 January 2020. Permission was granted on 17 March 2021, 14 months later. The site became operational on 1 January 2023, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6834.