Solar planning in Neath Port Talbot

Neath Port Talbot has decided 12 solar farms and approved 100% of them, taking a median of 5.7 months to decide. Consented capacity: 51 MW.

100%
Approved
12 granted · 0 refused
5.7 mo
Median decision
UK 2.3 mo
51 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Neath Port Talbot compares

Against the 298 UK authorities with 5+ solar decisions, Neath Port Talbot sits in the 77th percentile for approval rate (7 points above the England average) and the 4th percentile for speed.

Decisions by year

35Approved — 1 (2013)113Approved — 3 (2014)314Approved — 1 (2015)115Approved — 1 (2016)116Approved — 2 (2020)220Approved — 1 (2021)121Approved — 2 (2022)222Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (13)

SchemeMWStatusDecided
Sun Fields, Gelli Bwch Farm -Solar Array
Hale Construction Limited · P2023/0356 · 22.9 mo to decide
1.3Awaiting Construction2025-04-22
Dyfed Reinforcements, Riverside Road - Solar Panels
Associated British Ports · P2022/0643 · 1.1 mo to decide
0.36Awaiting Construction2022-09-29
Margam - Solar panels
Infinite Renewables Group Limited · P2022/0477 · 1.1 mo to decide
0.37Awaiting Construction2022-07-21
Ffordd Amazon, Crymlyn Burrows Solar Pannels
Pegasus Planning Group · P2021/0121 · 0.9 mo to decide
Awaiting Construction2021-03-10
Mynydd y Gwryhd Solar Farm
Awel Aman Tawe · P2020/0408 · 5.6 mo to decide
2.3Awaiting Construction2020-11-27
Swansea University Bay Campus
Swansea University Estates · P2020/0504 · 1.9 mo to decide
0.2Operational2020-08-20
Baglan Bay Solar Farm - Phase 2
St. Modwen Developments · P2015/0304
10Application Withdrawn2020-03-11
Caergarw Farm
Suncredit UK (Sunventures 7) · P2015/0692 · 5.8 mo to decide
3.8Operational2016-05-17
Maesgwyn solar farm
Walters Group · P2014/0762 · 9.7 mo to decide
7.5Operational2015-05-28
Pant-Y-Moch Farm
Canadian Solar · P2014/0567 · 4.1 mo to decide
5Operational2014-10-31
Tylerfedwen Farm Solar Park
Private Developer · P2013/1087 · 7.1 mo to decide
13.3Planning Permission Expired2014-07-22
Hendre Fawr Farm
INRG Solar · P2013/0635 · 9.6 mo to decide
11.6Operational2014-07-06
Baglan Bay Solar Farm - Phase 1
St. Modwen Developments · P2011/0054 · 23.9 mo to decide
5Operational2013-01-30

Does Neath Port Talbot approve solar farms?

Yes — of the 12 solar farms Neath Port Talbot has decided, 100% were approved (12 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Neath Port Talbot?

The median time from application to decision is 5.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Neath Port Talbot consented?

51 MW has been consented across 12 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Neath Port Talbot

Battery storage in Neath Port TalbotOnshore wind in Neath Port Talbot

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.