Renewable sitesPioneer 2 - Hydrogen Production Facility

Pioneer 2 - Hydrogen Production Facility

Pioneer 2 - Hydrogen Production Facility is a 2.5 MW hydrogen plant under construction in Neath Port Talbot. Planning permission was granted on 23 June 2025, 3 months after submission. Operator of record: Protium Green Hydrogen Supply Limited.

2.5 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Hydrogen
Technology
Protium Green Hydrogen Supply Limited
Neath Port Talbot
Authority
Wales

Planning and build timeline

Application submitted1 April 2025
Permission granted23 June 2025
3 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Neath Port Talbot: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pioneer 2 - Hydrogen Production Facility’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.6 km
Landfill Gas · Operational
23.8 km
Landfill Gas · Operational
2.24 km
Solar Photovoltaics · Operational
54 km
Solar Photovoltaics · Operational
0.24.1 km
Wind Onshore · Operational
85.9 km
Biomass (dedicated) · Operational
146.1 km
Solar Photovoltaics · Operational
106.8 km

How big is Pioneer 2 - Hydrogen Production Facility?

Pioneer 2 - Hydrogen Production Facility has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pioneer 2 - Hydrogen Production Facility?

REPD records the operator as Protium Green Hydrogen Supply Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pioneer 2 - Hydrogen Production Facility approved and built?

The application was submitted on 1 April 2025. Permission was granted on 23 June 2025, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 18704.