Renewable sites › Baglan Bay Solar Farm - Phase 1
Baglan Bay Solar Farm - Phase 1
Baglan Bay Solar Farm - Phase 1 is operational in Neath Port Talbot with a recorded capacity of 5 MW, and has been generating since 2014-03-30.
Planning and build timeline
| Application submitted | 2011-02-01 |
| Permission granted | 2013-01-30 24 months after submission |
| Operational | 2014-03-30 14 months after consent |
Neath Port Talbot’s record on solar
Neath Port Talbot has decided 12 solar farms and approved 100%, taking a median of 5.7 months. See every solar farm decision in Neath Port Talbot →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pioneer 2 - Hydrogen Production Facility Hydrogen · Under Construction | 2.5 | 0.6 km |
Swansea University Bay Campus Solar Photovoltaics · Operational | 0.2 | 3.5 km |
Briton Ferry Landfill Gas · Operational | 2 | 3.7 km |
Briton / Neath Landfill Gas · Operational | 2.2 | 3.8 km |
Pant-Y-Moch Farm Solar Photovoltaics · Operational | 5 | 4.6 km |
Carn Nicholas Farm (Extension) Solar Photovoltaics · Operational | 10 | 6.2 km |
Carn Nicholas Farm Solar Photovoltaics · Under Construction | 5 | 6.2 km |
Mynydd Brombil Wind Farm Wind Onshore · Operational | 8 | 6.5 km |
How big is Baglan Bay Solar Farm - Phase 1?
Baglan Bay Solar Farm - Phase 1 has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Baglan Bay Solar Farm - Phase 1?
REPD records the operator as St. Modwen Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Baglan Bay Solar Farm - Phase 1 approved and built?
The application was submitted on 2011-02-01. Permission was granted on 2013-01-30, 24 months later. The site became operational on 2014-03-30, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2381.