Brynwhilach Solar Park

Brynwhilach Solar Park is an operational 4 MW solar farm in Swansea, generating since 1 November 2021. Planning permission was granted on 4 November 2014, 4 months after submission. Operator of record: Core Pisces / Gower Power Co-op CIC.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 November 2021
Solar Photovoltaics
Technology
Core Pisces / Gower Power Co-op CIC
Swansea
Authority
Wales

Planning and build timeline

Application submitted16 July 2014
Permission granted4 November 2014
4 months after submission
Operational1 November 2021
84 months after consent

Screening a site of your own?

RedlineUK · £39

Swansea approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Brynwhilach Solar Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Swansea’s record on solar

Swansea has decided 16 solar farms and approved 88%, taking a median of 4.5 months. See every solar farm decision in Swansea

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
0.9 km
Solar Photovoltaics · Operational
61.7 km
Solar Photovoltaics · Operational
7.71.7 km
Solar Photovoltaics · Operational
62.8 km
Solar Photovoltaics · Operational
46.7 km
Solar Photovoltaics · Operational
106.9 km
Solar Photovoltaics · Under Construction
56.9 km
Wind Onshore · Operational
32.87.1 km

How big is Brynwhilach Solar Park?

Brynwhilach Solar Park has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Brynwhilach Solar Park?

REPD records the operator as Core Pisces / Gower Power Co-op CIC. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Brynwhilach Solar Park approved and built?

The application was submitted on 16 July 2014. Permission was granted on 4 November 2014, 4 months later. The site became operational on 1 November 2021, 84 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1975.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode