Sundridge Hill

Sundridge Hill is a 49.5 MW battery storage site under construction in Medway. Planning permission was granted on 17 August 2018, 9 months after submission. Operator of record: RNA Energy.

49.5 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
RNA Energy
Medway
Authority
England

Planning and build timeline

Application submitted14 November 2017
Permission granted17 August 2018
9 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Medway approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Sundridge Hill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Medway’s record on battery storage

Medway has decided 7 battery storage schemes and approved 100%, taking a median of 1.8 months. See every battery storage scheme decision in Medway

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.56.4 km
Battery · Operational
296.8 km
EfW Incineration · Operational
5110.2 km
Battery · Operational
1110.3 km
Battery · Operational
15010.7 km
Solar Photovoltaics · Operational
511 km
Solar Photovoltaics · Operational
4.711.5 km
Solar Photovoltaics · Under Construction
10.211.8 km

How big is Sundridge Hill?

Sundridge Hill has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Sundridge Hill?

REPD records the operator as RNA Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Sundridge Hill approved and built?

The application was submitted on 14 November 2017. Permission was granted on 17 August 2018, 9 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7081.