Renewable sitesBarvills Solar Farm

Barvills Solar Farm

Barvills Solar Farm is an operational 5 MW solar farm in Thurrock, generating since 29 March 2017. Planning permission was granted on 7 August 2015, 5 months after submission. Operator of record: BE Renewables/Barvills Solar Limited.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 29 March 2017
Solar Photovoltaics
Technology
BE Renewables/Barvills Solar Limited
Thurrock
Authority
England

Planning and build timeline

Application submitted19 March 2015
Permission granted7 August 2015
5 months after submission
Operational29 March 2017
20 months after consent

Screening a site of your own?

RedlineUK · £39

Thurrock approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Barvills Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Thurrock’s record on solar

Thurrock has decided 17 solar farms and approved 94%, taking a median of 2.4 months. See every solar farm decision in Thurrock

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
3.92.4 km
Landfill Gas · Operational
3.82.4 km
Battery · Operational
1503.2 km
Solar Photovoltaics · Operational
44.9 km
Battery · Operational
3.84.9 km
Biomass (dedicated) · Operational
435.3 km
Wind Onshore · Operational
126.2 km
Landfill Gas · Operational
4.59.1 km

How big is Barvills Solar Farm?

Barvills Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barvills Solar Farm?

REPD records the operator as BE Renewables/Barvills Solar Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barvills Solar Farm approved and built?

The application was submitted on 19 March 2015. Permission was granted on 7 August 2015, 5 months later. The site became operational on 29 March 2017, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5942.