Novarly ParcelRenewable sites

Renewable sitesAylesford BESS

Aylesford BESS

Aylesford BESS is operational in Tonbridge and Malling with a recorded capacity of 29 MW, and has been generating since 2020-06-01.

29 MW
Capacity
as recorded in REPD
Operational
Status
since 2020-06-01
Battery
Technology
Zenobe
Tonbridge and Malling
Authority
England

Planning and build timeline

Application submitted2017-09-05
Permission granted2017-12-05
3 months after submission
Operational2020-06-01
30 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
BIOSSENCE SOLAR PARK
Solar Photovoltaics · Operational
4.51.8 km
Allington EFW
EfW Incineration · Operational
514 km
Kingshill Solar Farm
Solar Photovoltaics · Operational
36.4 km
Sundridge Hill
Battery · Under Construction
49.56.8 km
Offham Landfill Site - Solar PV Array
Solar Photovoltaics · Under Construction
10.26.9 km
Offham Landfill Site Phase II
Landfill Gas · Operational
1.27.3 km
Land off Ford Lane
Solar Photovoltaics · Operational
4.77.9 km
Stangate Landfill Site
Landfill Gas · Operational
4.511.7 km

How big is Aylesford BESS?

Aylesford BESS has a recorded installed capacity of 29 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Aylesford BESS?

REPD records the operator as Zenobe. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Aylesford BESS approved and built?

The application was submitted on 2017-09-05. Permission was granted on 2017-12-05, 3 months later. The site became operational on 2020-06-01, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 20398.

Novarly Parcel · official public data, read properly · parcel.novarly.com