Renewable sitesAylesford BESS

Aylesford BESS

Aylesford BESS is an operational 29 MW battery storage site in Tonbridge and Malling, generating since 1 June 2020. Planning permission was granted on 5 December 2017, 3 months after submission. Operator of record: Zenobe.

29 MW
Capacity
as recorded in REPD
Operational
Status
since 1 June 2020
Battery
Technology
Zenobe
Tonbridge and Malling
Authority
England

Planning and build timeline

Application submitted5 September 2017
Permission granted5 December 2017
3 months after submission
Operational1 June 2020
30 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Tonbridge and Malling: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Aylesford BESS’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.51.8 km
EfW Incineration · Operational
514 km
Solar Photovoltaics · Operational
36.4 km
Battery · Under Construction
49.56.8 km
Solar Photovoltaics · Under Construction
10.26.9 km
Landfill Gas · Operational
1.27.3 km
Solar Photovoltaics · Operational
4.77.9 km
Landfill Gas · Operational
4.511.7 km

How big is Aylesford BESS?

Aylesford BESS has a recorded installed capacity of 29 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Aylesford BESS?

REPD records the operator as Zenobe. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Aylesford BESS approved and built?

The application was submitted on 5 September 2017. Permission was granted on 5 December 2017, 3 months later. The site became operational on 1 June 2020, 30 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 20398.