Broadditch Battery Energy
Broadditch Battery Energy is operational in Dartford with a recorded capacity of 11 MW, and has been generating since 2023-03-01.
Planning and build timeline
| Application submitted | 2018-05-14 |
| Permission granted | 2018-08-16 3 months after submission |
| Operational | 2023-03-01 54 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Green Belt — Dartford
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dartford’s record on battery storage
Dartford has decided 5 battery storage schemes and approved 80%, taking a median of 5.2 months. See every battery storage scheme decision in Dartford →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
St Margaret's Farm - Green Waste Composting Facility Biomass (dedicated) · Under Construction | — | 4.9 km |
Tilbury Docks Wind Onshore · Operational | 12 | 4.9 km |
Tilbury Green Power Biomass (dedicated) · Operational | 43 | 5.4 km |
Thurrock Flexible Generation Plant Battery · Operational | 150 | 6.2 km |
Tilbury LCY2 Solar Photovoltaics · Operational | 4 | 6.3 km |
London Distribution Park Battery · Operational | 3.8 | 6.3 km |
Littlebrook Battery Storage Battery · Operational | 7.5 | 7.5 km |
Longreach STW - extension Sewage Sludge Digestion · Operational | 1.1 | 8.9 km |
How big is Broadditch Battery Energy?
Broadditch Battery Energy has a recorded installed capacity of 11 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Broadditch Battery Energy?
REPD records the operator as Harmony Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Broadditch Battery Energy approved and built?
The application was submitted on 2018-05-14. Permission was granted on 2018-08-16, 3 months later. The site became operational on 2023-03-01, 54 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 20328.
Novarly Parcel · official public data, read properly · parcel.novarly.com