Allington EFW

Allington EFW is operational in Maidstone with a recorded capacity of 51 MW, and has been generating since 2008-12-01.

51 MW
Capacity
as recorded in REPD
Operational
Status
since 2008-12-01
EfW Incineration
Technology
Kent Enviropower (FCC Environment)
Maidstone
Authority
England

Planning and build timeline

Application submitted1998-08-14
Permission granted2000-07-13
23 months after submission
Operational2008-12-01
101 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
BIOSSENCE SOLAR PARK
Solar Photovoltaics · Operational
4.53.8 km
Aylesford BESS
Battery · Operational
294 km
Kingshill Solar Farm
Solar Photovoltaics · Operational
37.3 km
Offham Landfill Site - Solar PV Array
Solar Photovoltaics · Under Construction
10.28.7 km
Offham Landfill Site Phase II
Landfill Gas · Operational
1.29.2 km
Sundridge Hill
Battery · Under Construction
49.510.2 km
Land off Ford Lane
Solar Photovoltaics · Operational
4.710.4 km
Stangate Landfill Site
Landfill Gas · Operational
4.513.5 km

How big is Allington EFW?

Allington EFW has a recorded installed capacity of 51 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Allington EFW?

REPD records the operator as Kent Enviropower (FCC Environment). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Allington EFW approved and built?

The application was submitted on 1998-08-14. Permission was granted on 2000-07-13, 23 months later. The site became operational on 2008-12-01, 101 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 886.