Novarly ParcelRenewable sites

Renewable sitesLand off Ford Lane

Land off Ford Lane

Land off Ford Lane is an operational 4.7 MW solar farm in Tonbridge and Malling, generating since 17 November 2016. Planning permission was granted on 30 November 2015, 4 months after submission. Operator of record: Trina Solar.

4.7 MW
Capacity
as recorded in REPD
Operational
Status
since 17 November 2016
Solar Photovoltaics
Technology
Trina Solar
Tonbridge and Malling
Authority
England

Planning and build timeline

Application submitted23 July 2015
Permission granted30 November 2015
4 months after submission
Operational17 November 2016
12 months after consent

Screening a site of your own?

RedlineUK · £39

Tonbridge and Malling approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land off Ford Lane’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Tonbridge and Malling’s record on solar

Tonbridge and Malling has decided 8 solar farms and approved 88%, taking a median of 1.8 months. See every solar farm decision in Tonbridge and Malling

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.21.9 km
Solar Photovoltaics · Under Construction
10.22.3 km
Solar Photovoltaics · Operational
34 km
Landfill Gas · Operational
4.54.1 km
Battery · Operational
297.9 km
Solar Photovoltaics · Operational
4.59.7 km
EfW Incineration · Operational
5110.4 km
Battery · Under Construction
49.511.5 km

How big is Land off Ford Lane?

Land off Ford Lane has a recorded installed capacity of 4.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land off Ford Lane?

REPD records the operator as Trina Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land off Ford Lane approved and built?

The application was submitted on 23 July 2015. Permission was granted on 30 November 2015, 4 months later. The site became operational on 17 November 2016, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5572.