Novarly ParcelRenewable sites

Renewable sitesLand off Ford Lane

Land off Ford Lane

Land off Ford Lane is operational in Tonbridge and Malling with a recorded capacity of 4.7 MW, and has been generating since 2016-11-17.

4.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-11-17
Solar Photovoltaics
Technology
Trina Solar
Tonbridge and Malling
Authority
England

Planning and build timeline

Application submitted2015-07-23
Permission granted2015-11-30
4 months after submission
Operational2016-11-17
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Tonbridge and Malling’s record on solar

Tonbridge and Malling has decided 8 solar farms and approved 88%, taking a median of 1.8 months. See every solar farm decision in Tonbridge and Malling

Other built sites within 15 km

SiteMWDistance
Offham Landfill Site Phase II
Landfill Gas · Operational
1.21.9 km
Offham Landfill Site - Solar PV Array
Solar Photovoltaics · Under Construction
10.22.3 km
Kingshill Solar Farm
Solar Photovoltaics · Operational
34 km
Stangate Landfill Site
Landfill Gas · Operational
4.54.1 km
Aylesford BESS
Battery · Operational
297.9 km
BIOSSENCE SOLAR PARK
Solar Photovoltaics · Operational
4.59.7 km
Allington EFW
EfW Incineration · Operational
5110.4 km
Sundridge Hill
Battery · Under Construction
49.511.5 km

How big is Land off Ford Lane?

Land off Ford Lane has a recorded installed capacity of 4.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land off Ford Lane?

REPD records the operator as Trina Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land off Ford Lane approved and built?

The application was submitted on 2015-07-23. Permission was granted on 2015-11-30, 4 months later. The site became operational on 2016-11-17, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5572.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council